Toward
a Well-Functioning
Western Electricity Market:
Improving Western Resource
Assessment
West-Wide
Resource Assessment Team
Committee on Regional Electric Power Cooperation
January, 2003
I. Introduction and Background
At the fall 2002
CREPC meeting, the western RTOs made presentations on major elements of market
design. In the discussion regarding
resource adequacy, one common theme expressed by all three RTO representatives
was the importance of developing mechanisms for resource accounting that
provide an accurate west-wide assessment that ensures consistency and no
double-counting of resources by market participants and regulators. This was considered far preferable to a
mandate from the FERC that could result from their Standard Market Design (SMD)
proposal.
As follow-up to this
suggestion, an ad hoc group of technical staff of western state energy
regulatory and planning agencies[1]
reviewed the current status of west-wide resource assessment. Topics considered
by the west-wide resource assessment team (WRAT) included: (1) review of
ongoing resource assessment efforts; (2) analytic tools available to assist
such evaluations; (3) goals of assessments; and (4) specific approaches to
assessing the adequacy of the western interconnection (WI) and its
sub-regions.
It is important to
emphasize the purpose of the effort reported on here is not to evaluate or
assert what level of resource availability is or is not adequate. Our purpose
is to assess the need for and identify options to establish a west-wide
resource assessment process that evaluates potential load/resource balances
under various conditions in future years.
Annual resource assessments would provide a tracking mechanism to assist
regulators, utilities and independent suppliers making procurement and
investment decisions. A robust, consistent assessment could give regulators
early warning and reduce the chances of a repeating the 2000-2001 crisis.
WRAT participants
conducted three informal conference calls to evaluate resource assessment
activities underway in the West and to provide initial recommendations. (Highlights of technical discussions are in
Appendix A.)
There
are currently four west-wide resource assessment processes, each using a
different analytic approach or model.
The Northwest Power Planning Council (NWPPC), the California Energy
Commission (CEC), and the Western Electricity Coordinating Council (WECC) have
all prepared long-term demand and supply assessments for many years. Seams Steering Group-Western Interconnection
(SSG-WI) through its Transmission Planning Work Group (PWG) is embarking on
regional transmission planning studies to coordinate the efforts of the
California Independent System Operator and two proposed new regional
transmission organizations – WestConnect and RTO West.
The
NWPPC and CEC modeling efforts, which attempt to characterize the energy
markets they focus on in considerable detail, are summarized in Appendices B
and C. (Though Appendix B describes the
Council’s price forecasting model, it does not describe its Northwest
reliability assessment which is a separate effort using a different
model.) These efforts not only provide
forecasts of peak demand and supply, but also considerable analytic detail in
forecasting price and availability of fuels, capital costs of new facilities,
and other essential factors necessary to model the economic behavior of market
participants.
Appendix
D outlines the annual WECC 10 Year
Coordinated Plan Summary and summarizes recent related discussions of the
WECC Board. The WECC effort is
west-wide, but is limited to a peak hour forecast of loads and resources and is
a compilation of materials provided by member utilities. The accuracy of WECC’s assessment depends on
the accuracy of voluntary submittals from control area members. These inputs are not as rigorously examined
as the inputs to the NWPPC and CEC modeling efforts. In the most recent 10 year assessment, for example, the WECC
report projected that by August 2005, the West would enjoy reserve capability
of 86,743 MW compared with total peak demand of just over 140,000 MW (a 60%+
planning reserve). In the
California/Mexico sub-region alone, the WECC report forecasted that over
25,000+ MW of new generation would come on line between 2003 and 2005 when it is now clear that financial reality
has caused delay or cancellation of many of these expected facilities.
The
emerging SSG-WI PWG effort is focused on transmission expansion and is not
intended to provide annual load/resource balance assessments (Appendix E). It is proving difficult at this time to
define study goals and obtain data from participants, so success of this effort
is uncertain.
III.
Conclusions
WRAT participants have concluded that none of the current assessment efforts is sufficiently comprehensive and robust for the entire WI or its interrelated sub-regions.
While
the WECC planning process is a west-wide resource assessment, as noted in the
discussion at the WECC Board meeting on December 12-13, 2002, verifiability of
inputs is an important challenge. This
can be addressed in part if states and CREPC participants encourage utilities
to provide complete and consistent information and help scrub input
assumptions. Improvements to the
spreadsheet accounting approach used by WECC, (currently in progress at the
CEC), could allow increased flexibility in the analytic approach. However, as a peak day analysis it does not
address energy constraints that are important in the
Northwest, which relies on hydro generation.
Also, a compiled peak-day analysis has difficulty addressing coincident
regional peaks and the seasonal diversity of the WI.
We also have
concluded that the current NWPPC, CEC, SSG and WECC efforts all are limited by
inadequate data collection to provide a robust assessment for the entire
WI. The NWPPC and CEC inherently focus
on WI sub-regions and have incomplete data on loads and resources for the
portions of the WI outside their respective jurisdictions. Because sub-region imports and exports are
critical, a west-wide internally consistent assessment remains elusive. The WECC effort is limited in part by its
historic role as a voluntary reliability council and the inability to compel
participants (and non-participants) to provide complete and consistent
information, nor to critique that information once it is received. The SSG-WI PWG activities focus on
transmission planning and do not currently address resource adequacy. Coordination and data exchange between the
SSGWI PWG transmission modeling efforts and WECC, currently being pursued,
should enhance the value of both products.
Finally,
WRAT participants conclude that an on-going, robust resource assessment process
is needed and that such an annual assessment of expected load/resource balances
would serve multiple purposes:
·
Utilities guided by
state commissions and other regulatory oversight processes, are making
procurement decisions on the basis of their understanding of the overall
electricity market. These decisions can
best be informed by analysis of prospective overall WI and sub-regional
load/resource balances. If many others
are short, each utility may wish to cover a greater proportion of its load with
contractual commitments to protect its customers from wholesale price
volatility. Conversely, if overall WI
and sub-regional expectations are for surpluses, then spot market purchases may
be less costly than contractual commitments.
The relatively short or long positions of the Northwest particularly,
and the West generally, can be exacerbated or mitigated by annually varying
water conditions. Providing annual
updates on western load/resource balances will encourage and inform the better
decision making.
·
It will help to
identify specific sub-regions that have emerging problems, and to determine
whether these problems will impact the overall WI.
·
It would help guide
any needed regional action on this issue.
If the assessment indicates risks are low in the near term, this can
assure decision-makers that drastic measures are not urgently needed. This could allow the West time to craft
thoughtful and workable solutions to assure adequate resources and important
elements of market design.
Alternatively, if risks are moderate and increasing, it could spur quicker
action to avoid a crisis. Visible
regional oversight may also forestall pre-emptive FERC decisions regarding RTO
operation or Standard Market Design requirements.
Preliminary
recommendations focus on four areas: improvement in data gathering for
demand-side and supply-side resources; completion of a near-term load/resource balance assessment; support
for continuing CREPC cooperation with WECC and SSG-WI processes; and,
institutionalization of a robust, annual west-wide resource assessment process.
A comprehensive data
collection and review process for loads, resources and transmission facilities
would enhance results for any of the four assessment efforts now underway. Each entity spends considerable effort
scrubbing data to rectify problems and uncovering data not now available to
that entity. A comprehensive data
collection effort involving all utilities, energy service providers,
generators, and transmission owners in the WI, using regulatory and policy
guidance to ensure that data is provided in an accurate and timely manner,
would greatly improve load/resource assessments. Such an effort may require the legal authority of the various
states and could address data confidentiality and access limitations to ensure
that legitimate trade secrets are protected.
Completion of a
Near-Term Assessment
The WRAT discussions
reached consensus that it would be valuable to complete a short-term
assessment, utilizing existing information and ongoing work to the maximum
extent feasible. We propose an
assessment for 2004, provided sometime late in 2003, comparing 2004 to base
cases of 2000 and 2002. The assessment
could also be extended to 2006, but forecasts of loads and generation additions
beyond a year or two are much less certain, and therefore of lower value. For this initial assessment, it is
recommended that a variation of the ongoing wholesale power price forecasting
work of the NWPPC be used. For this
effort, the modeling would estimate the likely frequency of load curtailment as
one measure of load-resource balance.
The initial results of this work would be presented at the April 2003
CREPC meeting.
CREPC members are
representatives on the WECC Board and state technical staffs are presently
participating in SSG-WI working groups.
Continued participation and support is important in improving the
ongoing assessments and allowing increased cooperation between public and
private sector efforts.
Institutionalization
of a Robust Annual West-Wide Assessment Process
States/Provinces
should endorse the institutionalization of a robust annual, west-wide
assessment process. Additionally,
states/provinces should evaluate and recommend how an annual assessment should
be implemented. Possible options include:
·
Strengthening of the existing WECC
Coordinated Plan Summary by improving the quality of data employing additional
analytic tools, and improving the transparency of information;
·
Developing a joint
product completed by WECC and SSG-WI with appropriate state and regional
regulatory oversight; and/or,
·
States/provinces
independently, through CREPC, WGA or WICREPC (if established), develop an
annual assessment.
Additional work is
needed to develop a clear understanding of the viability and desirability of
these and other options. Completion of
multiple assessments that ask related questions but rely on a common data base may
be one logical outcome, so the options described above are not necessarily
mutually exclusive.
Technical Discussion of Alternative Assessment Methods
Multiple existing
accounting techniques or models for assessing adequacy exist. These include the annual WECC 10-Year Coordinated
Plan Summary and three WECC-region hourly production cost modeling
efforts. The four major analytic tools
are:
·
Spreadsheet
accounting balance tools used by WECC in 10 Year Summary
·
ABB Market Simulator
the SSG-WI planning workgroup is using;
·
Aurora model used by
the NWPPC;
·
GE MAPS or Henwood
models the CEC uses for it annual assessment and,
None of these methods
of assessment methods was rejected.
Each has some potential advantages.
A spreadsheet approach may be preferable for simplicity and
transparency, since there is no goal of forecasting price or other variables
that are simulated in complex production cost or market models.
Because of
transmission constraints inside WECC, an integrated assessment of the three or
four subregions is needed. The decision
on whether or not to combine the Rocky Mountain Power Area with the Arizona,
New Mexico, Southern Nevada Power Area does not have to be made now. It is more of an issue of how the data are
reported.
The CEC is working on
improving a transmission-constraint spreadsheet model that is used in the WECC
annual assessment. This has the
advantages of lower cost and is consistent with the only existing annual
assessment. The disadvantage is it
relates only to a few peak hours of the year and not to all the hours of
interest. Also, there is limited
opportunity to fix mistakes or remove dated data from the assessment. This method can identify the peak-day
capacity reserve margins under low-hydro conditions for the three or four
sub-regions.
The SSG-WI modeling
effort is focused on transmission expansion and congestion. It is progressing but not fully
established. The model will deal with
all hours and the data will be scrubbed by CREPC and utility participants. This approach is promising but uncertain.
Lack of data from non-RTO members could be a problem.
The Aurora, GE-MAPS
and Henwood models operated by the NWPPC and CEC are similar. All model the whole WECC region. They are available and reasonable. However, they do not have the active utility
participation of the WECC and SSG-WI methods.
To be used for an annual assessment the NWPPC or CEC models would need a
western public process to examine the inputs and assumptions. These models already have public processes
in the NW or California.
The group rejected,
at least for now, trying to calculate a loss-of-load probability (LOLP) for the
WECC region. The CEC and the NWPPC do
these kind of analyses, only for their own areas (CA and OR-WA-ID & W. MT,
respectively). These two efforts are
coordinated, but there are no similar efforts for the other six and a half
western states, or with British Columbia or Alberta.
Building an LOLP
model for the WECC would be a mammoth undertaking. Also, the likelihood an accurate probability estimate is
low. In addition, reducing LOLP is only
one of the goals of resource adequacy. It would not address the goals of
mitigating market power or reducing wholesale price volatility. Challenges for modeling the WECC-regions
LOLP include assessing detailed hourly transmission constraints in stressed
conditions, demand responses (both price and programmatic, short-term and
long-term) and the likely withholding of generation by participants with market
power.
The Northwest Power
Planning Council periodically prepares a forecast of wholesale electricity
power prices. The forecast includes a
base case that assumes continuation of current trends, and assessments of the
sensitivity of the base forecast to significant variables such as fuel prices,
electrical loads and energy policies.
The forecast represents the price of electricity as traded on the spot
market at the major trading hubs, such as the Mid-Columbia, under a
properly-functioning competitive market.
The forecast includes annual and monthly average prices for all hours,
and prices for low and high-load periods.
Hour-by-hour forecasts can be made for periods of interest once a base
forecast has been established. The
forecast period is from 2001 through 2025.
The Council’s
forecast is used internally for estimating the value of future resource
alternatives, including generation, conservation and demand response
options. In addition, the forecast is
used for estimating the cost of policies that might affect the composition or
operation of the future power system.
The price forecast is also used as an input into the Council’s risk
assessment portfolio model, currently under development. The model used for the forecast also permits
tracking of other variables of interest including fuel consumption and selected
environmental effects. Others use the
Council’s forecast for their own purposes.
The
forecast is prepared using the AURORA Electric Market Model, a proprietary
forecasting model developed by EPIS of West Linn, Oregon. AURORA is a economic fundamentals model,
capable of modeling entities ranging in size and complexity from an individual
load-serving entity to the principal North American interconnections. The area of interest is modeled as one or
more “load-resource areas”, generally defined by long-distance transmission
bottlenecks. Power prices are forecast
by identifying the marginal cost of serving load for each load-resource area
for user-defined sample hours of the period of interest. The marginal cost is the variable cost of
the most expensive generating unit required to meet load for the hour, or, for
some peak load hours, the cost of curtailing load in lieu of generation. Native or imported energy may be used to
meet load. The variable cost of a
generating unit includes variable fuel, operation and maintenance costs,
variable long-distance transmission costs, applicable variable environmental
costs and a user-defined dispatch premium.
Each load-resource area is characterized by its inventory of existing
generating units, forecasts of the prices of major fuels, a load forecast,
hydropower characteristics, and a portfolio of future generating resource
options. The transfer capacity, losses
and cost of major transmission links between the load resource areas is also
defined. Because future loads are
fixed, demand response is modeled as blocks of supply-side resources, each
defined by a quantity of energy available at given cost.
The base Council
forecast is for the Mid-Columbia trading hub in eastern Washington. Because of the strong electrical
interconnections between the Pacific Northwest and other WECC areas, the
Council models the entire WECC interconnected system, using the following
load-resource areas:
Load-resource areas
can be subdivided or consolidated as desired by the user. Expanding the number of load-resource areas
allows more precise definition of load-resource area characteristics and the
transmission relationships to other load-resource areas, and can be useful in
modeling a single load serving entity where resources, loads and contracts are
well-understood. However, each
additional load-resource area requires the development of significant and
credible input data. Moreover, model run
times increase with additional load-resource areas, and problems with model functionality
may be encountered with load-resource areas having significant resources but
little load, or vice-versa. Finally,
unintuitive local resource expansion or retirement results may be encountered
when subdividing load-resource areas.
Load-resource areas
can be consolidated by redefining load-resource areas and combining the
associated input data. Alternatively,
the user can define area consolidations for which the model will automatically
consolidate certain output data, such as prices and demand. This feature can be useful for examining
larger regions such as WECC sub-areas.
Once the modeling
structure and basic data are defined, the forecasting effort follows a two-step
modeling process. First, an
economically optimum schedule of future resource additions and retirements is
developed by means of a long-term optimization study, using the endogenous
system expansion logic in AURORA. The
fundamental assumption is that resources will be built if they can yield a
defined return at market prices. Conversely, resources that cannot yield a return will not be built
or, if existing, will be retired. In
this step, AURORA tests alternative resource additions and retirements,
developing over a series of iterations, a least-cost, economically optimum schedule. Once a satisfactory optimization is achieved
and a least-cost schedule of resource additions and retirements identified,
dispatch (pricing) studies can be run to explore hourly, monthly and annual
prices for the various load-resource areas and hubs.
The extensive input
data and assumptions required for the forecast are developed with the
assistance and review of the Council’s Fuel, Demand and Generating Resource
advisory committees. Fuel price and
demand forecasts are available for public review through the Council’s issue
paper process. The power price forecast
overall studies is accomplished with the specific assistance of the Council’s
Generating Resources Advisory Committee.
Appendix
C
Resource
Assessment Modeling of the CEC
The California Energy
Commission (CEC) periodically simulates the operation of the WECC electricity
market for extended periods into the future (as far out as ten years). It does
so in order to assess the likely values of important variables (wholesale spot
market prices, natural gas demand by the electric generation sector, congestion
frequency and costs on major transmission lines, frequency and extent of
involuntary curtailments, emissions levels for nitrogen oxide and carbon
dioxide, etc.) under a range of assumptions regarding future natural gas
prices, resource additions and retirements, etc. The forecast includes a base case and assessments of the
sensitivity of the base forecast to significant variables such as fuel prices,
electrical loads, hydro conditions, resource additions and retirements and
energy policies. The forecast
represents the price of electricity as be traded on the spot market at the
major trading hubs under a properly-functioning competitive market.[2]
Hourly prices from
the model are used to value demand-side programs and ‘creative’ tariffs, assess
the value of flexible supply-side resources, etc. But while the model generates
hourly prices, it cannot replicate the volatility observed in wholesale spot
markets during 1998 – 2002 (this inability is a result of several factors,
including increased volatility in actual natural gas markets as compared to the
stylized ‘average’ monthly prices used as modeling inputs, and short-term
derates of major transmission lines).[3]
Accordingly, the hourly prices from modeling efforts are routinely
‘volatilized’ using actual hourly (spot market) price series from prior years.
The forecast is
prepared using the MarketSymÔ model, a proprietary forecasting model developed by Henwood
Energy Services, Inc. of Sacramento. MarketSym is a “bottom up” economic
fundamentals model. Power prices are
forecast by identifying the marginal cost of serving load in each hour of the
period of interest. The marginal cost
is the variable cost of the most expensive generating unit required to meet
load for the hour, or, for some peak load hours, the cost of curtailing load in
lieu of generation. The variable cost
of a generating unit includes variable fuel, operation and maintenance costs,
variable long-distance transmission costs, and applicable variable
environmental costs. The model emulates both regulated and unregulated markets,
requiring that participants in the latter offer power at marginal production
cost, but allowing participants in the latter to offer power at a higher ‘bid’
price, which allows for recovery of start-up and no load costs, debt payments,
and ‘scarcity rents’ during periods in which operating margins are low,
requiring the dispatch of relatively inefficient units. The extent to which
generators are apt and able to offer power at prices in excess of variable
production cost is estimated by benchmarking resulting market prices to those
observed during 1999 – 2002.
The base Commission
forecast is for the three transmission areas in the California ISO control
area.. Because of the strong electrical
interconnections between California and other WECC areas, the Commission models
the entire WECC interconnected system as 25 load-resource areas. Each load-resource
area is characterized by its inventory of existing and forecasted generating
units, forecasts of the prices of major fuels, a load forecast, and hydropower
characteristics. Because loads can be served by units in non-native
load-resource areas, the total transfer capability (TTC), losses and (wheeling)
costs of transmission links between the load resource areas must also be
defined. WECC data is used in specifying the TTCs.
Demand inputs include
annual peak and energy values[4]
for each utility (monthly values may be used but are not necessary) for each
year to be simulated. The energy is then allocated across the 8760 hours of the
year based on a utility-specific load shape (8760 hourly values representing a
‘synthetic’ demand profile facing the utility, itself an approximation based on
5 – 10 years of historical data. The utility-level estimates of hourly load are
then aggregated to the transmission-area level.
Interruptible load
programs are modeled by representing them as a supply-side resource. This
resource is described by its (strike) price(s) and available quantity(ies); the
unit is dispatched (load is curtailed) when the market clears at or above the
specified price. While it is possible to specify the price at which load is
curtailed, as well as limit the curtailment to specific hours of the day or
months of the year, it is not possible
to limit the total number of hours per year (or month, week) that curtailment
occurs, or to curtail load at specified
operating reserve levels. Staff traditionally prices curtailment programs
at levels in excess of generating units, but below the cost of spinning reserve
violations and unserved energy. This effectively makes curtailment a
‘last-resort policy, used only to avert MORC violations.’
Demand side
management (efficiency, load-shifting) programs must be represented on the
demand side by specifying the impact of the program on the load-shape and/or
the peak and energy values. This is a laborious task that involves a great deal
of ‘flair.’ The impact of a program which reduces load by 2% during summer
afternoons is modeled by reducing the relevant values in the load shape by 2%,
then reducing the annual energy requirement by the indicated amount (0.1 -
0.12%).
Programs which induce
changes based on price elasticity (e.g., real time pricing) must use one of the
above two approaches. This means that the response at each price must be
assumed (modeling as a supply-side resource) or the a priori (quantitative) effect of the program in each hour must be
assumed. It is not possible to have the
model endogenously determine load given a demand elasticity.
Unlike the Aurora
model used by the Northwest Power Planning Council, Marketsym ä does not
endogenously value potential or existing resources; i.e. it cannot provide a market-driven, much less optimal set of
resource additions and/or retirements.[5]
Assumptions regarding short-run (two years or less) decisions are based on
information available to the user regarding the permitting and construction of
new facilities and announced plans regarding placing existing units in cold
standby. Longer run assumptions regarding additions and retirements are based
on the user’s judgement regarding responses to the market conditions forecasted
by the model.
The extensive input
data and assumptions required for the forecast are developed by the vendor and
Commission staff, in cooperation with regulatory agencies throughout the WECC
and in Washington D.C. Fuel price and
demand forecasts are available for public review, as are input data not
developed under proprietary license or secured pursuant to confidentiality
agreements. CEC staff have exogenously verified and updated many of the model
inputs, allowing us to provide them to third parties for use under certain
conditions.
Excerpts from
the Western Electricity Coordinating Council
10-Year Coordinated Plan Summary 2002-2011,
and
Notes of WECC Board Discussion 12/12-13/02.
http://www.wecc.biz/documents/publications/WECC_10-Year_Coordinated_Plan_Summary_2002-2011.pdf
Published September 2002
From
page 1
This annual report provides [in]formation concerning the
reliability and adequacy of the planned WECC interconnected bulk power system,
and includes:
·
an assessment of bulk power system reliability;
·
uncertainties and the potential effects;
·
historical load and resource information;
·
projected peak demand and energy load growth; and
·
planned generation and transmission facilities.
The ten-year (2002-2011) coordinated plans of the WECC
organizations are as of January 1, 2002.
From
page 10
WECC
Assessment Process
The evaluation of
reliability within the WECC region is performed using a comprehensive annual
assessment process based on the following established reliability criteria:
·
Power Supply Assessment Policy;
·
Minimum Operating Reliability Criteria; and,
·
NERC/WECC Planning Standards.
Adherence to these criteria provides an objective and
deterministic evaluation of the adequacy of the western interconnected power
system.
Resource
Assessment
The resource assessment process in the WECC region has
been in place for many years and is prepared for the four sub-regions of WECC.
A resource assessment on a region-wide basis is not appropriate because of
transmission constraints.
Resource adequacy is assessed by comparing the sum of
the individual member reserve requirements (determined by criteria) for a
sub-region with the projected reserve capacity. WECC is currently refining its
resource adequacy assessment practice in light of the changing electric
industry. WECC’s enhanced assessment methodology places additional emphasis on
transmission limitations between assessment areas within WECC.
At
present, the projected reserve capacity (margin) is determined by subtracting
the firm peak demand, exclusive of interruptible and controllable load
management peak demand, from the net generation and firm transfers. Net
generation and firm transfers are determined exclusive of inoperable capacity.
If the projected reserve capacity exceeds the reserve requirement, it is expected
that projected resources are adequate for the sub-region. On this basis,
projected reserve capacity is expected to be adequate throughout the WECC
region for the 2002 through 2011 ten-year period. The assessment assumes that
approximately 81,100 MW of net new generation will be built when and where
(Excerpts of summary notes
by Bill Chamberlain of December 12-13 meeting).
The Council used to
have a power supply criterion that included planning reserve margins for
resources. That was replaced by the
power supply assessment policy when duty to serve was dropped by some systems
as part of deregulation. There is an
ongoing problem in that these assessments reach conclusions that are driven by
the assumptions as to which new resources will come on line and which existing
resources will stay on line. The
assessment that is now being brought to the Board at this meeting shows much
more capacity coming on line in California over the next three years than the
amount we know will actually be completed.
WECC staff acknowledged that the conclusions are only as good as the
information they have available to them.
[See also, Board discussion of this issue, following paragraphs]
The
WECC resource adequacy assessment uses a simplified, spreadsheet model approach
to give a low cost picture of probable adequacy on a west-wide basis. The assessment considers peak demand,
existing resources, and planned additions, together with transmission capacity
between major load and resource zones.
There were many concerns expressed about the input data for the report
because many of the resources anticipated to come on line in the assessment
appear not to be likely at this point in time.
Thus the report seems to provide an overly optimistic view of resource
adequacy at this point. It was noted
that to the extent that the huge surpluses shown in the report are seen as
credible, that would suggest that power prices will be very low for a long
time. This would tend to cause existing
resources to be retired and new resource investments to be delayed. Also, generators will be reluctant to
provide an accurate prediction that older units will be retired because they
may give up emission credits by doing so.
The Board supported the approach the Committee has taken in using the
simplified spreadsheet approach but did not approve the report because of
concerns that its conclusions are inaccurate.
The Board accepted the report and gave direction that (1) data should be
solicited from more than just the control areas, and (2) the assessment should
be done twice a year. Bill Chamberlain
suggested that WECC staff and the PCC work closely with the California Energy
Commission in developing the assumptions that go into the California portion of
the assessment. The Northwest Power
Planning Council would also be a good source of information for the Northwest
portion of the assessment.
Excerpts from the Attachments to the Seams Steering Group-Western
Interconnection: January 8, 2002
Filing to the FERC
Transmission Planning Work
Group (PWG)
http://www.ssg-wi.com/documents/105-SSGWI_Report_Jan703Attachs.pdf)
Attachment B to
Report of the California ISO, the RTO West Filing Utilities,
and the WestConnect Applicants Concerning Activities of
the Seams Steering Group - Western Interconnection
Executed Memorandum of Understanding and Cooperation
Among RTO West, WestConnect, and the California ISO
[Excerpted]
SSG-WI 2002-03 Work Plan – Draft VERSION 1.1, July 19,
2002
2002-03 Work Plan - Planning WG:
Goal of the Planning WG –
To provide a forum to further
the development of a planning process that will result in a robust West-wide
interstate transmission system that is capable of supporting a competitive and
seamless West-wide wholesale electricity market.
Tasks of the Planning WG:
· Identify
Congested Paths and Load and Generation scenarios and perform studies for 2008
time frame.
· Review
tools available or under development to evaluate the benefits of transmission
projects to expand access to electricity markets and resources.
· Determine
load, generation and transmission scenarios to study in the 2013 time frame and
run studies.
· As
part of the above tasks, address the recommended “Next Steps” identified in the
August 2001 WGA report, “Conceptual Plans for Electricity Transmission in the
West”.
· Begin
work on development of a transmission Vision for future development of the
western transmission system.
[1] WRAT participants now include staff representatives of California, Montana, Wyoming, Washington, Utah, Nevada and Oregon regulatory agencies; and the Northwest Power Planning Council.
[2] The forecast considers that some classes of generators may be able to secure prices in excess of their variable operating costs during peak hours and under ‘tight’ supply-demand conditions. Their ability to do this is not endogenously determined, but specified by staff as an input. CEC staff utilized 1998 and 1999 market data in setting the relevant parameters.
[3] This is true even for relatively stable years (e.g., 1998, 2002), as well as for comparably stable markets.
[4] Net energy for load values are used; this is an estimate of the generation needed, including losses, to meet customer demand.
[5] The value of such functionality is questionable. If recent history proves anything, it is that investment decisions yield a far more cyclical path of additions than simple decision-rules might suggest. Retirement decisions are also based on considerations that are not easily captured by mathematical models.