UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY
COMMISSION
Electricity
Market Design and Structure Docket
No. RM01-12-000
NOTICE OF OPTIONS PAPER
(April 10, 2002)
Take notice that the Commission has
distributed an options paper for resolving rate and transition issues for
standardized transmission service and wholesale electric market design. The purpose of this paper is to stimulate
public discussion that can guide the development of a proposed rulemaking on
these issues. Parties filing comments
are requested to make recommendations on the options that should be included in
the proposed rulemaking as well as to address the pros and cons of the various
options contained in the paper.
The options paper is being placed in
the record of this rulemaking docket.
It will also be available on the Commission's website at
http://www.ferc.gov/Electric/RTO/mrkt-strct-comments/discussion_paper.htm.
Comments on this paper should be
filed with the Commission by May 1, 2002.
Comments may be filed in paper format or electronically. For paper filings, the original and 14
copies of the comments should be submitted to the Office of the Secretary,
Federal Energy Regulatory Commission, 888 First Street, N.E., Washington D.C.
20426. For electronic filings via the
Internet, see 18 CFR 385.2001(a)(1)(iii) (2001) and the instructions on the
Commission's web site under the "e-Filing" link. All comments will be placed in the
Commission’s public files and will be available for inspection in the
Commission’s Public Reference Room at 888 First Street, N.E., Washington D.C.
20426, during regular business hours.
Additionally, all comments may be viewed, printed, or downloaded
remotely via the Internet through FERC's Homepage using the RIMS link. User assistance for RIMS is available at
202-208-2222, or by e-mail to rimsmaster@ferc.gov.
Magalie R. Salas
Secretary
Options for Resolving Rate and Transition Issues in
Standardized
Transmission
Service and Wholesale Electric Market Design
The Working Paper on Standardized
Transmission Service and Wholesale Electric Market Design issued March 15,
2002, identifies several issues that require further discussion. These issues involve embedded cost recovery
under the proposed Network Access Service and transition issues involved moving
to one tariff for all service.
Specifically, the issues are: 1) the manner in which embedded costs of
the transmission system will be recovered; 2) the manner in which Transmission
Rights will be allocated among customers; and 3) the transition of customers
under existing contracts (real or implicit) to the new service. The Working Paper also identifies the issue
of long-term generation adequacy as an area where further discussion is
needed. This paper identifies options
the Commission has for resolving these issues.
Parties are requested to provide comments on the advantages and
disadvantages of these options. Parties
may also propose other options they believe the Commission should consider in
resolving these issues. These comments
will be used in developing proposals to be included in the Notice of Proposed
Rulemaking (NOPR) to be issued this summer.
Current Services and
Recovery of Transmission Revenue Requirements
Under the pro forma
tariff, there are two types of services that are used to transmit wholesale
power – Network Integration Transmission Service and Point-to-Point
service. In addition, Point-to Point
Service is available on a firm or a non-firm basis. Network Integration Transmission Service (Network Service) is
designed for load serving entities and can only be used to serve network
load. If the customer wants to serve
non-network load, it must do so under a separate Point-to-Point contract. There are no restrictions on the type of
entity that can buy Point-to-Point service.
Transmission providers (i.e., traditional public utilities) are
not required to take service under the pro forma tariff if the
transmission service is to be used solely to serve bundled retail load.[1]
A Network Service customer pays a
monthly demand charge based on its load ratio share of the transmission
provider's monthly transmission revenue requirement. The customer's load ratio share is based on the customer's hourly
load coincident with the transmission provider's monthly transmission system
peak. The Point-to-Point firm customer
pays a monthly demand charge for each unit of capacity that it has
reserved. Non-firm Point-to-Point
customers pay a charge for the capacity reserved for the service.
The two ISO's that currently use
Locational Marginal Pricing (LMP), PJM Interconnection, L.L.C. (PJM) and New
York Independent System Operator (NYISO), use the same three basic services,
but with changes to reflect the different pricing system under LMP. PJM sells firm Point-to-Point transmission
service.[2] The customer pays a demand charge for the
reserved capacity and will also be charged for the cost of congestion between
the requested source and sink if the customer does not have Financial
Transmission Rights for the source and sink.
PJM also sells non-firm Point-to-Point transmission service. In PJM, non-firm Point-to-Point service can
flow if the customer pays the cost of congestion. If the customer is unwilling to pay the cost of congestion, the
non-firm service will be interrupted when congestion occurs. The non-firm customer is charged the higher
of the demand charge for the reserved capacity or the congestion charge. The revenues received from non-firm service
each month are credited to the customers purchasing firm Point-to-Point or
Network Service in proportion to the charges they pay. PJM sells Network Service which is
consistent with the service contained in the pro forma
tariff. However, rather than
calculating the customer's load ratio share based on the transmission system's
monthly peak load (as in the pro forma tariff) the load ratio
share is calculated based on the transmission system's annual peak load.[3]
NYISO also offers Point-to-Point
(firm and non-firm) and Network Service.
However, in NYISO non-firm service is interrupted when congestion
occurs. If a customer is willing to pay
congestion costs to ensure the service will flow, the customer buys firm
service. The system will be
redispatched to support the firm transactions, both Point-to-Point and
Network. A transmission service charge
is charged all wholesale customers (Network, firm and non-firm Point-Point) to
recover the embedded cost of transmission owners. The transmission service charge applies to deliveries to load
within NYISO as well as wheel throughs and exports.[4] The transmission service charge is paid for
each MWh scheduled during the month.
Both PJM and NYISO use a license
plate rate design. With a "license
plate rate" the rate paid for transmission services varies depending on
where power is delivered within the RTO.[5] The license plate rate recovers the embedded
costs of the transmission owner of the facilities where power is delivered.[6] PJM and NYISO have different rate designs
for exports and wheel throughs. PJM
uses a weighted average of the charges of all transmission providers for these
types of transactions. NYISO uses the
transmission charge of the owner of the intertie which serves as the point of
delivery to the adjacent control area.
Changes Proposed in the
Services
The Working Paper proposes to blend
these three types of service into a new Network Access Service that could be
purchased by load serving entities as well as non-load serving entities. The service could be used to move power
between two points, a source and a sink.
A Network Access customer would have access to all sources and sinks on
the system. Under the Network Access
Service there would be two types of transmission related rights. The first is the Access Right, i.e.,
the right to move power between any two points on the system. The second is the Transmission Right, i.e.,
the right to a predetermined price for service between two specific points on
the system (the customer does not have to pay congestion charges for service between
those two points). Either the Access
Right or the Transmission Right could be used as the basis for recovery of the
embedded costs of the transmission system.
The Working Paper also proposes to
use LMP to manage congestion on the system.
Under an LMP system, the distinction between firm and non-firm service
is less important than under the current pro forma tariff. Except in very rare cases, a non-firm
service can be scheduled on any day if the customer is willing to pay the cost
of congestion.[7] The price for transmission service for
curtailable transactions may be high at times because of the cost of
congestion. The customer may respond to
those price signals by reducing its purchases of transmission service.
An access charge would be used to
recover the embedded costs of the system.[8] The same methodologies used by either PJM or
NYISO to recover the embedded costs of the transmission systems could be
used. However, Network Access Service
would differ from the existing pro forma services in that both
current Point-to-Point and Network customers would receive the same service.
This may necessitate a change in the methodology for recovery of embedded
costs.
Additionally, under the current rate
designs, a user that transmits power from one system to another pays two
transmission charges to recover the embedded costs of the system from which
power was exported as well as the embedded costs of the system where power is
delivered to load. In designing the
rates for Network Access Service, the rates could be designed to continue the
payment of multiple transmission charges or they could be designed so that only
one transmission charge is paid.
There are three main issues in
designing the access charge: 1) who pays the access charge for deliveries
within the transmission provider's system?; 2) should the access charge apply
to exports and wheel throughs?; and 3) is the charge billed based on peak load
or actual usage? The answers to these
questions will affect the allocation of costs among the various users of the
transmission provider's system. Each of
these issues is a separate question and the preference for a particular option
on one question should not determine the preference on another option. Finally, the rate treatment for exports and
wheel throughs should be consistent among transmission providers to avoid the
creation of artificial incentives or disincentives for trade across
regions. However, allowing regional
variations on the other two cost allocation issues may not have the same
potential for affecting regional trade.
Where there is an RTO in place, the Commission could permit flexibility
on the cost allocation decisions for that region.
Who
pays the access charge for deliveries within the transmission provider's
system?
Option 1: Access charge
applies to anyone that schedules deliveries within the transmission provider's
system, whether it be an import, service between a receipt and delivery node in
the system, or purchases of power by load from the energy markets. The general principle is that anyone that schedules
these transactions is receiving transmission service (the Access Right) under
Network Access Service. Since there is
only one service, all users of the service should be subject to the access
charge. Under this approach there could
be multiple access charges paid if there are intermediate transactions to get
power to load, e.g., a marketer aggregating generation at a trading hub
and a load serving entity buying power from the marketer at the trading hub.
Option 2: Access charge is paid only by customers that take power off the
grid. The general principle is that
load pays the access charge - only the customer taking ultimate delivery of the
power would pay an access charge.[9] Generators or marketers delivering power to
or between hubs would not pay the access charge. However, they would pay any applicable congestion charges and
losses.[10]
Option 3: Payment of access charges
and the receipt of Transmission Rights or the auction revenues from those
rights would be linked together. Payment
of the access charge to recover embedded costs could be tied to whether the
customer has protection against congestion charges or not. The access charge could be paid only by
customers that can be offered Transmission Rights or an allocation of revenues
from the sale of Transmission Rights.
Customers that do not receive these protections against congestion costs
would only pay congestion charges and losses for transmission service. If the new customer wanted Transmission
Rights it could either acquire them through an auction or pay for the
construction of new facilities in which case the customer would receive the
Transmission Rights for the added capacity.
Thus, under this option some customers would pay the access charge and
some would not.
Should
the access charge apply to exports and wheel throughs?
Option 1: The access charge
would apply to these transactions. These
transactions use the facilities within the transmission provider's system and
thus should pay for the use of these facilities. If the access charge is paid, it will be recovered in the
delivered price of power to the load that ultimately uses the power. It is
appropriate that these ultimate customers should contribute to the recovery of
the embedded costs of the transmission systems that were used to transmit the
power. This option continues the
current pricing policy for exports and wheel throughs.
Option 2: The access charge
would not apply to these transactions. A transaction originating in
one transmission provider's system and terminating at a load in another
transmission provider's system would only pay one access charge, the access
charge for the transmission system where power is ultimately delivered to load.
However, the transaction would still be responsible for applicable congestion
charges and losses in the originating and any intermediate transmission
systems. This option encourages broader
areas of competition by eliminating multiple access charges (pancaking of
rates).
Option 3: The access charge
would not apply to individual transactions.
But, there would be an annual revenue adjustment. As in option 2, a transaction originating in one transmission
system and terminating at a load in another transmission system would only pay
one access charge, the access charge for the transmission system where power is
ultimately delivered to load. However,
the aggregate transactions for the year would be taken into account in setting
the revenue requirements to be recovered through the access charges for each
transmission system. For example, if
RTO A were a net exporter through the year to neighboring RTO B, a pro rata
share of RTO A's revenue requirement would be allocated for recovery through
the access charge of RTO B. Thus, the
load in RTO B would contribute to the recovery of the embedded costs of RTO A.
Option 4: A lower access charge would apply to exports and wheel throughs than
for deliveries within the transmission provider's system. This option is a compromise between Option 1
and Option 2 – all customers would pay something for the use of the grid, but
the reduction (but not elimination) of multiple access charges for service
across neighboring systems would encourage a broader area of competition.
Is
the access charge billed based on peak load or total usage?
The Attachment to this paper
provides an illustrative example of how different rate designs can
significantly affect the cost impact on customers depending on their usage
patterns throughout the year. Rate
designs that allocate cost responsibility based on peak usage favor high load
factor customers whose use of the system at peak periods is close to their use
of the system at off-peak periods. Rate
designs that allocate costs on the basis of monthly peak usage will allocate
proportionately more costs to customers that use the system more extensively
during off-peak periods. Rate designs
that allocate cost responsibility based on annual usage, favor low load factor
customers whose use of the system at peak periods is much higher than their
annual use of the system.
Option 1: Use monthly peak
load for billing the access charge. This continues the
methodology that is contained in the current pro forma
tariff. Embedded costs represent sunk
costs that are unaffected by any usage or investment decision that customers
make now or in the future. Therefore,
the mechanism to recover these costs should be designed to have as little
effect as possible on current decision making, i.e., day-to-day usage of
the system. Continuation of the current
methodology in the pro forma tariff is consistent with this
rationale. Use of a monthly allocation
factor recognizes that different customers will have different load patterns
throughout the year. For example, some
customers may use the transmission system more during off-peak periods. A monthly allocation factor will capture
these differences in usage throughout the year.
Option 2: Use annual peak
load for billing the access charge. The same basic rationale as
in Option 1 for using a demand charge based on peak usage would also apply to
this option. Using annual peak load as
the allocation factor encourages customers to increase their load factor by
reducing their use of the system at peak periods. High load factor customers (customers whose load at peak periods
is similar to their load at off-peak periods) will pay less under this option
than under Option 1. Conversely, low
load factor customers (customers whose load at peak periods is much higher than
their load at off-peak periods) will pay more under this option than under
Option 1. Seasonal customers who do not
take service on the system peak may pay nothing for transmission service under
this option.
Option 3: Bill the access
charge for each MWh used. This methodology would bill
the costs to customers based on total use of the system and thus may be viewed
as an equitable way to allocate the costs among the customers. However, because the access charge would be
billed based on actual usage, it could affect decisions on the day-to-day usage
of the transmission system. This rate
design methodology produces the lowest cost responsibility for low load factor
customers who make much greater use of the system during peak periods than at
other times.
Transition of Customers
under Existing Wholesale Contracts and Bundled Retail Customers Load to
Transmission Service under the Revised Pro Forma Tariff
Some transmission problems currently
exist because customers under existing wholesale contracts and customers taking
bundled retail service have different terms and conditions of service than
those customers taking pursuant to an open access transmission tariff. For example, differences in scheduling terms
and conditions has resulted in transmission capability not being fully utilized
because of more favorable scheduling terms for customers under existing
wholesale contracts. With respect to
customers taking bundled retail service, transmission providers have tended to
favor those customers by preferentially reserving ATC for their future use and
reserving transmission capacity for reliability purposes (capacity benefit
margin) without directly assigning the costs to the customers benefitting by
the reservation. This is a particular
problem because customers taking bundled retail service comprise a majority of
total load.
A further problem also arises if
these non-pro forma tariff customers are not required to abide by
the same terms and conditions of service.
Because they generally comprise a large proportion of the total load, it
would be extremely difficult to implement a congestion management system, such
as LMP, for a transmission provider without placing this load under the tariff.
When standard market design is
implemented, there will need to be a transition process in place so that most
if not all of the transmission provider's customers will be taking service
under the new standard market design tariff.
Standard market design will apply both to service within an RTO as well
as service on systems that are not part of an RTO. A transition process will be needed in both cases. However, where there will be an RTO in place
when standard market design is implemented, the Commission could permit some
regional flexibility in designing a transition process.
Option 1: All service occurs
under an open access transmission tariff at the time standard market design is
implemented. If this approach is taken,
other transition steps would need to be taken to ensure that existing customers
continue to receive the approximate level and quality of service that they
previously received. One way to do this
would be to give existing customers the ability to convert to Transmission
Rights based on their historical use of the system.
Under this approach all transmission
customers would be treated the same way under the same terms and conditions of
service. This will make the
implementation of standard market design, including congestion management,
easier.
Option 2: Convert all
customers taking bundled retail service upon implementation of standard market
design and provide strong incentives for customers under existing contracts to
convert. Under this option, the Commission would
require all customers taking bundled retail service to take transmission
service under the revised tariff. However,
rather than require customers under existing wholesale contracts to take
service under the revised tariff, the Commission would encourage those
customers to convert to service under the revised tariff. For example, customers that convert to the
new Network Access Service would receive the additional flexibility available
under this new service. The Commission
could also provide customers that chose to convert to the new Network Access
Service with conversion rights to the allocation of Transmission Rights.[11] The Commission could impose restrictions on
changes to current contracts to ensure that customers can only get the
additional flexibility by converting to Network Access Service.
This option avoids the problem of
having to deal with contract abrogation.
It also would allow the Order No. 888 approach to these customers to
further play out. Under that approach,
if a customer modified, changed or revised an existing contract, it was
obligated to then take service under an open access transmission tariff.
As provided in Option 1, if this
approach is taken with respect to customers taking bundled retail service,
transition steps should be taken to ensure that these customers receive
approximately the same level and quality of service that they previously
received.
Option 3: Allow regional
variations. Under this option, the
Commission could permit the issue of how to convert customers under existing
wholesale contracts and taking bundled retail service to be decided on a
regional basis if there will be an RTO in place when standard market design is
implemented. This option would not be
available on transmission systems that would not be in an RTO. The Commission could allow each RTO to make
a proposal for converting these customers to service under the revised
tariff. If this approach is taken, the
NOPR would only give general guidelines on what would or would not be
acceptable. The specific mechanisms
would be developed by each RTO. Of
course, the Commission would need to analyze the proposals to ensure that the
regional variations do not create seams problems or interfere with the
implementation of standard market design.
Allocation of Transmission
Rights
There are several different
transition issues that arise when moving to an LMP system. Under an LMP system of congestion
management, Transmission Rights that provide protection against the cost of
congestion are potentially very valuable.
The initial allocation of these rights among customers is mainly a
question of equity and not efficiency.
As long as these Transmission Rights are defined so that they are
tradable property rights, an efficient market solution should result. However, the method that is used to make the
initial allocation can convey benefits on particular customers or classes of
customers.
Should
historical customers get the initial Transmission Rights ?
Option 1: Convert existing
customers' usage to the initial Transmission Rights. In
the Working Paper issued on March 15, 2002, one of the general principles
states that customers with existing contracts (real or implicit) should
continue to receive the same level and quality of service under standard market
design. If a transmission system has
constraint points, as most if not all do, then to satisfy this general
principle existing customers, many of which are load serving entities, should
receive a conversion right for the initial Transmission Rights. On a constrained system, more participants
will want Transmission Rights than can be issued. Participants that do not currently have contract rights will want
to acquire Transmission Rights for the constrained points. If the use of the system by existing
customers is not recognized in the transition mechanism, either through an
allocation of Transmission Rights or an allocation of the auction revenues for
these rights, there may be significant cost shifts because of congestion
costs. The objective of this option is
to preserve the service quality for the load served by the existing
customer. To recognize retail choice
and to not discourage the entry of new suppliers, if load moves from one load
serving entity to another, the Transmission Rights would move with the
load. This way the new supplier would
have access to Transmission Rights to serve the load.
Option 2: Give all customers
that pay access charges the same rights to Transmission Rights. Under Network Access Service the number of customers could
increase significantly. If all of the
Transmission Rights are assigned to the existing customers, there would be none
left to assign to any new customers. Earlier in this paper, the options for
assessing the access charge were discussed.
A decision on the billing of the access charge could affect the approach
that is taken on the initial allocation of Transmission Rights. The Commission could either allocate the
Transmission Rights or the auction revenues for the Transmission Rights to all
customers that pay the access charge.
Procedures would also be needed for reallocating the Transmission Right
or auction revenues as new customers are added. Such an approach would benefit new entrants because it would make
it easier for them to acquire Transmission Rights. However, it would likely significantly increase the costs of
transmission service (including congestion costs) to end-use customers.
If
existing customers are given the initial conversion rights, how should
Transmission Rights be allocated?
Option 1: Assign rights
based on existing contract rights and historical usage. The Commission could assign the Transmission Rights based on
existing sources and sinks in Point-to-Point contracts and the designated
resources for Network Integration Service and bundled retail load. In essence, those customers that currently
are using those points for firm service would get the right to continue to use
those points without paying for congestion.
In some cases, the requests for existing customers for Transmission
Rights between specific points may exceed the Transmission Rights that can
reliably be granted. In that case,
actual usage of those points in a recent historical period could be used to
allocate the rights among existing customers.
Usage of the system particularly by network customers changes over time. For example, peak load may increase more
rapidly in one service territory than another.
Or, the load of the traditional utility may decrease because of state
retail choice programs. Consequently,
the allocation of Transmission Rights may need to be regularly adjusted to
ensure that there continues to be an equitable allocation of Transmission
Rights.
This approach comes closest to
replicating the rights customers currently have under existing contracts or for
bundled retail load. However, under
this methodology it may be difficult for new entrants to acquire Transmission
Rights.
Option 2: Auction
Transmission Rights and assign the auction revenues based on existing contract
rights (real and implicit). Under this approach all
Transmission Rights would be auctioned.
This way the entity that values these rights the most would obtain
them. New entrants and existing
customers could obtain Transmission Rights through the auction. The revenues
from the auction would be allocated to existing contracts, primarily load. This would serve to reduce the total transmission
costs including congestion costs paid by these customers. Under an auction methodology load could
ensure that it gets the Transmission Rights by bidding high in the auction.[12]
Theoretically, Options 1 and 2
should produce the same end result if there is a secondary market for trading
Transmission Rights. However, some
existing customers have expressed doubts that it would. They are not certain that the auction revenues
would cover the congestion costs they may face. Additionally, there has been a more active secondary market for
Transmission Rights where there is an auction for Transmission Rights (NYISO)
rather than an allocation of Transmission Rights (PJM).
The auction methodology may be
preferred by load in states that have had significant divestiture of
generation. In those states, this
methodology may give load a better ability to hedge congestion costs when
buying from a variety of suppliers.
This type of methodology is used in NYISO and is proposed for use in
ISO-NE, both areas where there has been substantial divestiture of generation.
Option 3: Partial allocation
and auction. As a transition mechanism,
the Commission could permit a combination of the two methodologies. For example, 75% of the rights could be
allocated and 25% could be auctioned with the revenues allocated to existing
customers. Over time, an increasing
amount of the Transmission Rights could be auctioned. This method provides some opportunity for new entrants to acquire
Transmission Rights through the auction.
It also gives existing customers allocated Transmission Rights for most
of their load to provide a transition to a more competitive wholesale market.
Option 4: Allow regional
variation. Where an RTO will be in place when standard
market design is implemented, the Commission could permit existing customers on
each RTO to choose the methodology that will be used for the initial allocation
of Transmission Rights. This option
would not be available on transmission systems that are not part of an
RTO. As long as the Transmission Rights
are tradable property rights with the same characteristics, using different
allocation methodologies for the initial allocation will not create seams
problems. Because states have adopted different polices on generation divestiture
and retail choice, different allocation methodologies may better suit the needs
of the customers. For example, if there
has been little divestiture of generation on a system, an allocation of
Transmission Rights may permit customers to more closely replicate the service
they currently receive. On the other
hand, if most of the generation on a system has been divested, an allocation of
auction revenues may give customers more flexibility in buying from multiple
sellers. The Commission could find that
either method is acceptable and let the existing customers choose which method
better addresses their needs.
The Working Paper identified the
issue of ensuring adequate generation resources as a contentious issue that
needs further discussion. At the
conferences held in January and February, there was wide support for some type
of program either administered at a state, regional, or federal level. However, there were significant
disagreements over what the mechanisms should be to ensure long-term generation
adequacy as well as who should administer the program.
There are several different
approaches that could be used to design the forward-looking supply
obligation. Standard market design
would apply to transmission systems that are part of an RTO as well as to
transmission systems that have not joined an RTO. Parties are requested to comment on whether the same approaches
should be used in both instances or whether different approaches should be
used.
Option 1: Rely on energy
prices and information on projected supply/demand situation. This option would make load serving entities
responsible for acquiring sufficient supplies to meet their needs. This option assumes that energy prices will
reflect the supply/demand situation in the region and send the appropriate
price signals to investors.
Since energy markets are regional in
nature, an individual load serving entity may not have sufficient information
to assess the regional supply/demand situation. Therefore, the transmission provider would conduct and publish
studies projecting the short and long-term supply/demand situation for the
region as a whole. These studies would
also identify the supply/demand situation for the load pockets within its
area. These studies should provide the
market with information that can be used to project whether energy prices in
the area are likely to rise or remain stable.
It also would provide information on where new generation and/or demand
response programs are needed in the near future.
This information should provide load
serving entities with the information they need to make rationale choices to
minimize their total supply costs. Load
serving entities would determine the mix of supply sources, long-term and spot
purchases, that best meet their needs.[13] If the studies indicate that there will be a
large surplus of power in the region for the next several years, the load
serving entity may decide that it will rely more heavily on short-term
contracts. On the other hand, if the
studies show that supply conditions may be tightening in the near future, the
load serving entity may decide to hedge its future energy costs through
long-term contracts or other financial measures. The transmission provider should also develop load shedding
procedures that ensure, to the extent operationally feasible, that in times of
shortage, load shedding would be targeted to the load serving entities that did
not have adequate supplies.
Option 2: Require a regional
supply obligation. Each region would have a
single region wide supply obligation for all load serving entities in the
region, comparable to the traditional utility-specific reserve margin.[14] The obligation would be imposed on all load
serving entities within the region, e.g., a traditional utility or an
energy marketer serving retail loads.
The level of the supply obligation would be set within each region with
the active involvement of the state commissions in the region.
The transmission provider would
determine if each load serving entity in the region has enough supply to
satisfy its share of the regional supply requirement. The supply obligation could be satisfied by generation owned or
under contract, firm contracts for energy that are backed by specific
generation units or a portfolio of designated generation units, and demand side
resources that can be verifiably curtailed.[15] The firm contract would be for a forward
looking period selected based on the time needed to construct new generation, e.g.,
one to five years. The load serving
entity would also need to demonstrate that these generating units and demand
side resources are physically feasible, i.e., the units are capable of
generating the power planned or reducing the demand planned, and transmission
is available from the generating unit or demand resource to the individual load
serving entity.[16]
There are two different types of
enforcement mechanisms that could be used.
First, if the load serving entity did not meet the regional supply
requirement, it could be required to file a curtailment plan with the
transmission provider. This way there
would be an up front understanding that a load serving entity that fails to
satisfy the regional supply obligation would be among the first curtailed in a
shortage and the method of curtailment is understood by all from the
outset. Alternatively, a load serving
entity could be required to satisfy the regional supply obligation as a
condition of receiving an allocation of Transmission Rights or an allocation of
the auction revenues from the sale of those rights.
Option 3: Require a regional
capacity obligation. Under this option there would
be an obligation for load serving entities to obtain capacity resources for
both energy and reserves similar to the capacity obligations that are currently
in effect in the three Northeastern ISOs.
As with the prior option, each region would set a region wide capacity
obligation with the active participation of state commissions. The transmission provider would also
determine the capacity obligation for each load serving entity. As in Option 1, the capacity obligation
could only be satisfied by the load serving entity demonstrating that it owned
or had contracts with generators or marketers for specific generating units and
demand response sources.
The major differences between this option and Option 2 are in the
timing of the supply obligation and the enforcement mechanisms. Under this option there would be an ongoing capacity
obligation. To satisfy the capacity
obligation the load serving entity would need show that it had met the capacity
obligation for the month or season before the beginning of that month or
season. Under Option 2 the supply obligation would be for a longer period (e.g.,
one to five years) and the load serving entity would have to demonstrate that
it satisfied this obligation at least several months in advance.
The enforcement mechanism under this
option is that a load serving entity would be subject to an administrative
penalty based on the capital cost of a new generating unit for the amounts it
was deficient. The transmission
provider would also administer markets for load serving entities that are short
to acquire capacity credits from generators that have excess capacity to
sell. The administrative penalty would
serve as a de facto upper limit on the price of capacity credits sold in these
markets.
Option 4: Impose a supply
obligation on load serving entities only if projected reserves fall below a
trigger level. Under this option on an annual basis each
region would make a region wide projection of future demand for energy with an
appropriate reserve margin e.g., 15%-18% and future supplies
available. State commissions would play
an active role in this process. If this
region wide projection shows that the region will have adequate supplies for
future needs, e.g., projected needs one to three years in advance, then
there would be no supply obligation on load serving entities. If this region wide projection shows that
there are not adequate supplies for the future, then each load serving entity
would have a supply obligation. When
the region was short the supply obligation could be similar to the supply
obligations described in Options 2 and 3.
The same conditions on generating units or demand side resources that
could be used to satisfy the supply obligation could also apply. Conceptually, either an administrative
enforcement mechanism like those described in Option 2 or a penalty and
capacity market enforcement mechanism like that described in Option 3 could be
used. However, if the supply obligation
would only be triggered in certain years, an administrative enforcement
mechanism would likely be the more cost effective option.
Option 5: Capacity
obligations for operating reserves only – forward reserves contracts. Under this option the transmission provider would
acquire an option on generation that could be used to provide reserve capacity
at some time in the future or would assign to load serving entities the
requirement to procure such reserve capacity.[17] The transmission provider or the load
serving entity would buy a call option on energy to be produced in the
future. Sellers would offer various
options available at different strike prices.
Accepted sellers would be required to submit bids on a daily basis to
supply energy at the designated strike prices.
The buyer could select from these various options to specify the strike
prices at which energy would be sold if called upon. Alternatively, the option could be structured so that if exercised,
the energy could be sold at the market clearing price. If the RTO transmission provider would
procure the options for reserve capacity for the region as a whole, individual
load serving entities would receive a bill for their share of the cost of reserve
capacity. Consequently, there would be
no need for an enforcement mechanism such as a deficiency charge, since load
serving entities would not be required to procure their own options on future
reserve capacity. However, by procuring
generation capacity, the transmission provider would be taking a position in
the market. Alternatively, if load
serving entities are assigned the requirement to procure the options,
transmission providers would not take a position in the market. However, if load serving entities are
assigned the requirement, a mechanism would be required to enforce the
requirement.
Attachment
Simplified
Example:
Sample
Customers and Rate Designs for the Access Charge
Customers:
(1) Load serving entity serving high
load factor industrials (e.g. a manufacturer running around the
clock): 100 MW per hour all hours
(2) Load serving entity serving
seasonal users (e.g. a ski resort):
0-100 MW per hour, seasonal use
(3) Load serving entity serving
residential customers (lighting, air conditioning): 50-300 MW per hour, varies by season
Customer Usage
at System Peak Hour, by month (MW)
NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT
(1) 100 100 100 100 100 100 100 100 100 100 100 100
(2) 100 100 100 100 100 50 0 0 0 0 0 50
(3) 50
50 50 50 50 50 100 100 150 300 150 100
Totals 250 250 250 250 250 200 200 200 250 400 250 250
Effects on
Load Ratio Share of the Three Rate Options
12-month Avg
Peak Annual Peak Usage Method**
Total Peak Total
Peaks Avg. LRS* (Aug) LRS Usage LRS
(1) 1200 100 40% 100 25% 1200 57%
(2) 600 50 20% 0
-0- 300 14%
(3) 1200 100 40% 300 75% 600 29%
Totals 3000 250 400 2100
*
Load Ratio Share
**
Assumes that the monthly usage rate is ˝ of peak hour usage. For simplicity and since the object is to
determine the load ratio share, the calculations above do not take the steps of
multiplying out the hourly usage rate times the number of hours in the month.