D. Transmission
Pricing
1. The
Commission seeks to ensure transmission owners the opportunity to recover their
revenue requirements for their transmission systems under Network Access
Service. This charge could either be a
license plate rate (charge depends on zone of delivery) or a postage stamp rate
(same rate applies for all load within the Independent Transmission Provider's
service area) and would be paid by all entities serving load within the
Independent Transmission Provider's service area. Moreover, to facilitate trading across regions, we are proposing
to change our policy on pricing of transactions that start and end in different
transmission systems.
2. In addition,
we are proposing to refine our policy on pricing of transmission expansions to
provide incentives for market-driven solutions. To facilitate the addition of much needed transmission
infrastructure, we propose a regional approach to transmission expansion which
includes extensive participation by Regional State Advisory Committees102 to identify the beneficiaries of a
proposed expansion and how costs for that expansion should be recovered.
1. Recovery of Embedded Costs
3. Under the
existing pro forma tariff, there are two types of transmission
services – Network Integration Transmission Service, which is designed for the
integration of resources and loads, and Point-to-Point Transmission Service,
which is generally used to export power from one transmission system to another
(through-and-out service).
4. To recover
the embedded costs of the transmission grid, the Commission has historically
permitted transmission providers to assess an access charge, in the form of a
load ratio share charge or a per kW per month charge, on all transactions
taking place on the transmission provider's system.103
For a single transmission utility, these charges usually take the form
of a "postage stamp" rate (i.e., the same charge for all
customers' use of the utility's grid) and, for an ISO or RTO, a "license
plate" rate (i.e., a different charge for the use of the entire
regional transmission system that is based on the revenue requirement of the
transmission owner's facilities, or "zone," where the transaction
sinks).104 The access charge is
assessed on all transactions making use of the transmission provider's system,
including transactions where the generator and load are located within the
transmission provider's system and where either the generator or the load (or
both) are located outside of the transmission provider's system.
5. While this
method of pricing has been effective in recovering a transmission provider's
revenue requirement, some changes are required to reflect the new Network
Access Service and to address unintended consequences of the current rate
design. First, we propose that transmission
owners recover embedded costs through an access charge assessed mainly to
load-serving entities, based on their respective shares of the system's peak
load, i.e., their load ratio shares.
Our goal is to minimize the distorting effects that an access charge can
have on economic choices. We propose to
assess access charges primarily on loads, but not on generators, because the
economic choices of loads (such as where to locate) are less likely to be
affected by access charges than are the choices of generators.105
Moreover, even if access charges were imposed on generators or other
market participants, it is likely that they would pass along most or all of
their access charges to their customers, so that loads would ultimately bear
most or all of the transmission fixed costs.
6. Second,
we propose to eliminate all "rate pancaking," which involves charging
separate embedded cost charges for moving power over separate Independent
Transmission Provider service areas. We
propose to eliminate rate pancaking both within an Independent Transmission
Provider's service area and between service areas. Rate pancaking impedes the ability of distant generators to
compete with nearby generators by imposing charges to transmit energy from
distant generators that are unrelated to actual variable transmission
costs. Assessing the access charge
primarily to load-serving entities based on their load ratio share rather than
on the number of service areas over which energy is transmitted increases
generation competition by allowing distant generators to compete more easily
with nearby generators.
7. As discussed
further below, we propose that customers paying access charges would receive
Congestion Revenue Rights (or alternatively, revenues from the auction of
Congestion Revenue Rights). Thus, in
exchange for paying the fixed costs of the transmission system, those paying
access charges would receive the financial benefits – the stream of congestion
revenues – resulting from usage of the transmission system. In addition, we seek to minimize cost shifts
that could result from our proposal, and we propose to maintain as much as
possible the explicit and implicit transmission rights currently held by
customers. Thus, customers currently
receiving Network Integration Transmission Service and firm Point-to-Point
Transmission Service under the existing pro forma tariff would receive
Congestion Revenue Rights based on their existing service levels. However, there are two issues regarding
access charges and the allocation of Congestion Revenue Rights on which we
specifically seek comment.
8. First, we
seek comment on the treatment of existing customers taking long-term firm
Point-to-Point Transmission Service that are not load-serving entities. Such customers currently pay an embedded
cost charge in order to receive firm Point-to-Point Transmission Service under
the Order No. 888 pro forma tariff.
We believe that it would be inequitable for customers to receive an
initial allocation of Congestion Revenue Rights unless they also pay a share of
transmission embedded costs. We also
believe that it would be inequitable for customers to pay a share of
transmission embedded costs without receiving an initial allocation of
Congestion Revenue Rights. Thus, we
seek comment on two options. One option
is for these customers to continue paying their embedded cost charges in
exchange for receiving Congestion Revenue Rights that reflect their current
levels of Point-to-Point Transmission Service.
This option would help minimize cost shifts, while maintaining the
transmission rights currently held by these customers. On the other hand, this option would recover
a portion of embedded transmission costs from customers that are not loads. The second option is to eliminate the access
charges for these customers while also allocating no Congestion Revenue Rights
to them. This option avoids recovering
embedded costs from entities that are not loads. However, it would result in some shifting of the responsibility
for recovering embedded costs, and it would fail to maintain the transmission
rights currently held by these customers.
We seek comment on the merits of these two options, as well as whether
the Final Rule should select one option or, alternatively, allow customers to
choose between them.106
9. The second
issue concerns the treatment of load-serving entities in retail open access
states that attract loads away from their traditional utility suppliers. Under our proposal, a new load-serving
entity that attracts load from other suppliers would be assigned a share of
embedded costs – costs previously assigned to other suppliers. In areas where there is no Available
Transfer Capability for additional Congestion Revenue Rights, we seek comment
on how such new load-serving entities should receive an allocation of the
customer's former load-serving entity's Congestion Revenue Rights. We propose that Congestion Revenue Rights
"follow the load." Thus, Congestion
Revenue Rights previously allocated to other suppliers whose loads (and access
charges) have been reduced would be reallocated to the new load-serving
entities.
10. We
propose to permit the use of license plate rates such as those that are
currently in effect within ISOs. We
seek comment, however, on whether we should retain license plate ratemaking
only for a transitional period and at some later date, require that all regions
have postage stamp rates. Should the
Commission upon the recommendation of a Regional State Advisory Committee
accept an embedded cost recovery mechanism for the region which may vary from
neighboring regions?
11. To
better illustrate the pricing proposals we have included Appendix F which
identifies by customer types whether and under what circumstances they will pay
the access charge and/or receive Congestion Revenue Rights under Network Access
Service.
2. Rates
for Bundled Retail Customers
12. When
a vertically integrated utility joins a regional organization such as an ISO or
RTO, the Commission has required that the utility execute a service agreement
under the regional transmission provider's transmission tariff. For instance, the Commission required the
vertically integrated utilities in GridSouth to execute a service agreement
under the GridSouth transmission tariff, thus ensuring that these utilities
would take service for their bundled retail load under the same terms and
conditions as all other users of the grid.
13. With
respect to whether the GridSouth transmission charge should be applied to the
bundled retail load, the Commission permitted the utilities to pay the
transmission portion of the bundled retail rate, but required that the service
agreement explicitly state the rate to be charged.107
The Commission added that having vertically integrated utilities pay
GridSouth for transmission to serve their bundled retail customers does not
make those utilities' retail rates subject to our jurisdiction. Rather, the Commission stated its
willingness to accommodate the utilities paying GridSouth a transmission rate
equal to the transmission component of their bundled retail rates, as long as
the price is clearly stated, reduced to writing in contracts with GridSouth,
and is not accomplished by omission.108
14. Now
that the Commission is asserting jurisdiction over all transmission service in
interstate commerce, including that for bundled retail service, the question
arises as to whether different charges for transmission service for wholesale
and bundled retail customers should be permitted. Allowing different rates for wholesale and bundled retail
customers could lead to undue discrimination if the rate setting policies of
the state and the Commission differ significantly. The Commission seeks comment on whether all customers should be
charged the same transmission rate either upon implementation of Standard Market
Design or after a reasonable transition period of four years.
3. Inter-Regional
Transfers
15. Under
current rate designs, a user that transmits power from one region to another
would pay two transmission charges to recover the embedded costs of the transmission
provider from which power was exported as well as the embedded costs of the
transmission provider where power is delivered to load. As long as transmission owners have an
opportunity to recover their embedded costs, to increase competition, we propose
to prevent customers from being assessed multiple transmission charges.
16. We
have concluded that rate treatment for inter- and intra-regional transactions
should be consistent to avoid creating artificial incentives or disincentives
for trade across regions. Thus, the
design of rates for Network Access Service should eliminate the payment of
multiple access charges, such that only one access charge is paid for power to
reach load. Accordingly, an export and
through-and-out transaction originating in an Independent Transmission
Provider's system and terminating at a load in another Independent Transmission
Provider's system would pay only the access charge for the transmission system
where power is ultimately delivered to load.109
This will encourage broader areas of competition by eliminating multiple
access charges, and in particular would reduce the harsh inequities of regional
boundary definition on those customers near such boundaries.
17. It
has become apparent that transmission pricing across RTO borders can have a
significant impact both on power purchasing decisions and on RTO
formation. A customer's choice as to
whether to purchase power from a generator located within the same RTO or a
neighboring RTO is directly affected by the fact that one generator faces an
additional access charge to reach the RTO in which the load is located. This additional access charge may cause the
sale to become uneconomic.110
18. In
addition, decisions on which RTO/ISO to join may be affected by inter-regional
pricing. Choices driven by the
economics of transmission owner's merchant function's trading patterns, rather
than by the most rational and efficient aggregation of transmission assets for
a particular region, could result in oddly configured RTOs.
19. Rate
pancaking across the numerous transmission owning utilities that comprise the
RTO has been eliminated by the implementation of license plate rates, while
continuing to provide an opportunity for the transmission owners to recover
their full revenue requirements. We
propose that the same or a similar rate structure should be applied to
inter-regional transfers. In a
competitive market environment, reliability and the supplier's cost of
generation, rather than sunk transmission costs, should be the primary drivers
for a customer's choice of power suppliers.
To the extent rate design facilitates that result, transmission owners
would have a greater incentive to join an RTO based on where their transmission
facilities most benefit customers and markets, not on where their generators
have better opportunities to make off-system sales (i.e., an access
charge for exporting power from one region to a neighboring region should not
be the deciding factor).
20. However,
absent other adjustment mechanisms, if customers going through and out of an
RTO are no longer charged access fees by that RTO for transmission service,
these costs would instead be borne by the load served by the RTO through the
existing load ratio share methodology.111
Under the commonly used license plate rate design, load within a
particular RTO zone would pay that transmission owner’s full embedded costs,
including the portion that is currently contributed by through-and-out
customers. This may create problematic
cost shifts for certain transmission providers that currently receive a
significant amount of revenue from exports and wheel-throughs (e.g., AEP
and Cinergy). While simply eliminating
the transmission charge for through-and-out service may avoid the skewing of
purchase and sale decisions by inter-regional transaction charges, it will
result in cost-shifting and may stifle new transmission investment since state
regulators will not generally favor having their customers pay for facilities
that may primarily benefit other states.
21. Therefore,
we propose to create a mechanism that recognizes the import/export quantities
in establishing the revenue requirement to be recovered through the access
charge. We seek comment on two
approaches that could be used.
22. One
method would be to have the "source" Independent Transmission
Provider allocate a portion of its revenue requirement to the "sink"
Independent Transmission Provider's transmission customers. An Independent Transmission Provider's revenue
requirement could be reduced by the amount of revenues associated with
through-and-out service and that portion of the revenue requirement would then
be included as uplift in the scheduling charge paid by all customers of the
sink Independent Transmission Provider in whose service area the power sinks. Under this approach, costs would not be
shifted from the beneficiaries of the inter-regional transaction to the load on
the source side of the transaction. At
the same time, embedded cost recovery would not interfere with short-run
efficiency, since embedded costs would not be recovered in individual
inter-regional transactions, but would instead be recovered through uplift from
all customers in the zone of the sink Independent Transmission Provider. This method would require a projection of
inter-regional transfers and a rate filing to accomplish the re-allocation of
costs between Independent Transmission Providers. It would also require a decision as to how narrowly to focus the
cost allocation (e.g., RTO to RTO, export zone to import zone).
23. Alternatively,
under a revenue crediting approach, inter-regional transfers could be priced at
the load ratio share charge (or a similar transmission charge)112 and the inter-regional transaction
charges would be netted out over some time period (e.g., one month or one
year). This method would assign the
inter-regional charges to all customers within the sink Independent
Transmission Provider. The cost of
transmission on a neighboring Independent Transmission Provider associated with
net imported power could be charged to all of the net importing Independent
Transmission Provider's customers through the Independent Transmission
Provider's scheduling charge. The
revenues would be returned to all transmission customers within the net
exporting Independent Transmission Provider.
24. We
seek comment on whether there should be a uniform cost allocation of
inter-regional costs among all zones within an Independent Transmission
Provider's system. For instance, there
will likely be opposition to a region-wide charge by customers who do not
import power. To address this concern,
the inter-regional transfers could instead be netted out between zones within
neighboring Independent Transmission Providers. This way the costs would be assigned to all customers within the
import zone and the revenues would be returned to the export zone. These transmission costs could be assigned
to the zone where the power was imported as if the neighboring Independent
Transmission Provider's facilities were part of that zone. Likewise, the zone where exports leave an
Independent Transmission Provider would receive the transmission payments
associated with the exports. It is
possible that the revenue sharing plan used by ISOs with license plate rates to
resolve intra-ISO, interzone transactions could be broadened to encompass
inter-RTO transactions.
25. As
noted above, the proposed rule advocates treating inter- and intra-regional
transmission pricing the same. As
explained elsewhere, customers within the region who pay the access charge will
be entitled to Congestion Revenue Rights or the revenues from the auction of
those rights. We propose a similar
result for inter-regional transactions when customers in one region are paying
a portion of the embedded costs of another region. We seek comment on how to assign Congestion Revenue Rights to the
customers of the importing region. For
example, if Midwest ISO is a net exporter to PJM, customers on PJM’s system
will be obligated to pay a portion of Midwest ISO’s embedded costs. PJM’s customers could receive a
proportionate share of Midwest ISO's Congestion Revenue Rights.
4. Application of
Inter-Regional Pricing to Parallel Path Flows
26. To
the extent the Commission adopts a true-up methodology for recovering the costs
of through-and-out services, should a similar pricing methodology be applied to
parallel path flows? Parallel path
flows are comparable in that one region benefits by the use of a neighboring
region’s transmission facilities.
Parallel path flows are currently resolved through cooperation. An alternative method would be to price all
uses of the grid. We seek comment as to
how cost impacts of parallel path flows across regional borders should be
addressed.
5. Pricing of New Transmission Capacity
27. The
existing transmission grid has fallen far behind the demands that have been
placed on it. Over the last ten years,
we have seen a strong increase in the amount of new generation, which has been
built largely in locations that make the most economic sense for the builder of
the generation (i.e., where land is affordable and economic sources of fuel,
water and labor are near). However, we
have yet to see a parallel jump in construction of transmission
infrastructure. The absence of needed
new transmission facilities has led to more and more congestion, which hinders
customers from seeking and depending on more distant and competitive supply
choices.
28. The
sluggishness of transmission construction is largely because: (1) siting transmission is a long and
contentious process; and (2) mismatches between those who benefit from the new
facilities and those who pay for them, particularly when the two affected sets
of customers are served by different transmission providers, are often more
than enough to make sure the new facilities do not get built. The Department of Energy's 2002 National
Transmission Study points to state_by_state siting approval, a lack of regional
institutions and a lack of clarity in regulatory pricing policy as several of
the barriers to transmission investment.113
29. The
Commission's pricing policy for network upgrades, whether for reliability or
economic reasons, has traditionally favored "rolled in" pricing,
where all users pay an administratively determined share of new facilities. This policy was based on the rationale that
the transmission grid is a single piece of equipment such that system
expansions are used by and benefit all users due to the integrated nature of
the grid. This method forms the basis
of the pricing proposal in the Generation Interconnection proposed rule.
30. If
the expansion is for region-wide reliability, there is little disagreement as
to who should pay for the necessary facilities – all ratepayers. Likewise, interconnection facilities are
non_controversial; there is general agreement that these facilities should be
directly assigned to the interconnecting generator.
31. What
we see, however, is that economic expansions that would remove congestion and
allow customers to reach more distant power supplies are the most difficult to
get sited. This is at least in part
because state siting authorities have no interest in siting a line that
benefits a particular generator or a distant load in another state because to
do so would require the load on the constructing public utility's system to pay
for the new facilities. The state
authorities, at a minimum, need assurance that the costs of that expansion will
be paid for by those who benefit from the expansion in order to have sufficient
incentive to site the new facilities.
32. Our
goal is to remove any cost recovery impediments to transmission expansion so
that needed upgrades get built now.
Traditional means of expansion pricing may not be the most effective way
of encouraging new transmission infrastructure, in part perhaps because they do
not take into account the wide regional benefits of higher voltage upgrades
that can accrue beyond a single transmission owner's system.
33. We
believe that a more precise matching of beneficiaries and cost recovery
responsibility would encourage greater regional cooperation to get needed
facilities sited and built. Our
preference is to allow recovery of the costs of expansion through participant
funding, i.e., those who benefit from a particular project (such as a
generator building to export power or load building to reduce congestion) pay
for it.
34. The
Generator Interconnection proposed rule introduced the idea that participant
funding may be an acceptable pricing policy where an independent entity
determines: (1) the cost of and
responsibility for needed upgrades; (2) congestion price signals to which the
customer responds (along with Congestion Revenue Rights); and (3) the
assumptions underlying the power flow analysis.114
35. The
Commission envisions that, under Standard Market Design, the Independent
Transmission Provider will perform all of these functions, which will allow the
Commission to consider the use of participant funding. However, full compliance with Standard
Market Design will take some time. We
are eager to see new infrastructure in place as soon as possible and believe
that participant funding will be a useful tool to make that happen. Accordingly, we propose that, for proposed
transmission facilities that are included in a regional planning process which is
conducted by an entity, whether an RTO, ISO, or other independent entity, that
is independent, we will consider participant funding for that project.
36. In
the absence of independence, we would apply a default pricing policy that would
recognize the regional benefits of transmission expansions. Under this default policy, we propose to
roll_in on a region_wide basis all high voltage network upgrades of 138 kV and
above. Since lower voltage,
sub_regional transmission needs are less likely to benefit the whole region,
the cost of network facilities below 138 kV could be more appropriately
allocated to a sub_region (e.g., a single transmission owner or a
"license plate" zone) where the expansion facilities will be
located. Consistent with our proposal
for interregional transmission service pricing, costs would be allocated to the
region that benefits from the expansion, which may not be the same as the
region in which the expansion facilities are located. This proposal recognizes that high voltage expansions can have
benefits beyond the borders of the local transmitting utility and, therefore,
assigns a portion of these costs to more distant beneficiaries.
37. Further,
as we explain in Section IV.G.3, Regional Planning Process, we encourage the
formation of Regional State Advisory Committees, which, in addition to
facilitating the siting of regional expansions, can enable states to work
together to identify beneficiaries of expansion projects and make
recommendations on pricing proposals.
To the extent there is agreement within the Regional State Advisory
Committee, the Commission would look favorably on a pricing proposal by the
Regional State Advisory Committee if it is consistent with the FPA. Such a proposal might take the form of
roll_in, an assignment to beneficiaries, or some combination of the two.
We seek comment whether these pricing proposals are appropriate to meet our goal of expediting needed infrastructure investment or whether another method would be more effective.
102Regional State Advisory Committee as discussed more fully in Section IV.K.
103A Network Integration Transmission Service customer pays a monthly demand charge based on its load ratio share of the transmission provider's monthly transmission revenue requirement. The customer's load ratio share is based on the customer's hourly load coincident with the transmission provider's monthly transmission system peak. The firm Point-to-Point transmission customer pays a monthly demand charge for each unit of capacity that it has reserved.
104Both PJM and New York ISO use a license plate rate design. PJM and New York ISO have different rate designs for exports and wheel-through services. PJM uses a weighted average of the charges of all transmission for these types of transactions. New York ISO uses the transmission charge of the owner of the intertie that serves as the point of delivery to the adjacent system.
105Point-to-Point customers wanting to receive a direct allocation of Congestion Revenue Rights would also pay the access charge, as discussed below.
106We propose that Congestion Revenue Rights be directly assigned only to long-term firm customers, consistent with the existing pro forma tariff's right of first refusal. Thus, short-term and non-firm point-to-point customers would not receive Congestion Revenue Rights under direct assignment. These customers, therefore, may wish to structure their contracts such that they expire at the time Standard Market Design is implemented. This way, while they would not receive Congestion Revenue Rights, they also would no longer be paying an access charge.
107Carolina Power & Light Co., et al., 94 FERC ¶ 61,273 at 61,999, order on reh'g, 95 FERC ¶ 61,282 (2001).
10895 FERC ¶ 61,282 at 61,991.
109However, the transaction would still be responsible for applicable congestion charges and transmission losses in the originating and any intermediate transmission systems.
110E.g., a load and Generator 1 with a cost of $25 are located in RTO A, and a competing Generator 2 with a cost of $24 is located just across the border in RTO B. On its face (and absent congestion), it appears that the load should choose Generator 2 in RTO B. However, because Generator 2 faces a $2 transmission charge from RTO B, it is unable to compete with Generator 1 even though it is a more efficient unit simply because of the additional access charge.
111This would also be true for a non-RTO Independent Transmission Provider.
112An explanation of how this charge may be calculated is contained in Appendix F.
113See DOE National Transmission Grid Study.
114The Commission is currently reviewing extensive comments on this topic in that proceeding.