G. Other
Changes to Remove Undue Discrimination and Improve the
Efficiency
of the Markets under Standard Market Design
1. The existing pro
forma tariff was constructed primarily to apply to vertically integrated
public utilities. It was the first step
toward competitive electric power markets since it allowed alternate suppliers
to access loads through an open access transmission tariff. It sought to replicate the terms and
conditions under which the host public utility served its own loads. It also was the first step in separating the
generation and transmission arms of a public utility.
2. But more
changes are needed to further the development of regional competitive wholesale
electric markets and assure comparable and non-discriminatory treatment of all
market participants. Accordingly, the
following revisions must be made to the pro forma tariff to
change the market rules in ways that will improve the efficiency of wholesale
electric markets.
1. Capacity Benefit Margin
3. Capacity
Benefit Margin is the set-aside of transmission capability by a transmission
provider to ensure the ability to import external resources to meet generation
reliability requirements or in case of a generation capacity deficiency. During the Commission's outreach process, many
commenters asserted that Capacity Benefit Margin ties up valuable transfer
capability without a specific reservation and payment by the customers who
receive the benefit of the set-aside.
The subsidy occurs because, while part of the transfer capability is
withheld from the market as Capacity Benefit Margin, the wholesale transmission
customers using the system pay the entire transmission cost (including that of
the Capacity Benefit Margin) through their transmission charges, thus
subsidizing the Capacity Benefit Margin beneficiaries. The use of a Capacity Benefit Margin has
also been regularly challenged on the grounds that the host transmission
provider is withholding transfer capability under the guise of Capacity Benefit
Margin in order to thwart competition.
4. We propose to
standardize the treatment of Capacity Benefit Margin to ensure that (1) only
customers benefitting from it pay for it, and (2) transfer capability needed to
access resources on a neighboring system is treated consistent with all other
portions of the transmission grid.
Thus, an Independent Transmission Provider itself would not be permitted
to set aside transfer capability for generation reliability reasons. Rather, a load-serving entity wanting access
to resources on a neighboring transmission system to meet its resource adequacy
requirement should instead acquire Congestion Revenue Rights from the interface
to its load to ensure that access. This
will free up transfer capability now unavailable to wholesale transmission
customers and prevent cross-subsidization of transmission customers that serve
load within the Independent Transmission Provider's service area by
point-to-point transmission system users.160
5. This
prohibition of the generic set-aside of transfer capability by the Independent
Transmission Provider for generation reliability reasons does not apply to an
Independent Transmission Provider's responsibility to set aside transfer
capability to ensure transmission reliability (e.g., to ensure that a
line can take up the power flows it must absorb if a parallel line should go
out of service or other uncertainties in system conditions arise). Such a set-aside is called Transmission
Reliability Margin and must be consistent with good utility practice and should
not be implemented in a way that favors particular transmission customers (e.g.,
by release of the set-aside capability for use by native load).
2. Regional
and Independent Calculation of Available Transfer Capability, Performance of
Facilities Studies and OASIS
6. The Commission
has found specific instances of abuse by transmission providers regarding the
Available Transfer Capability calculation process and delays in the completion
of transmission facilities studies.161 There are obvious
incentives for a vertically integrated transmission provider to favor its own
generation by delaying facilities studies or manipulating the Available
Transfer Capability calculations or postings on its OASIS. Under Standard Market Design, calculations
of transmission capability and the performance of facilities studies for
transmission expansions must be performed by an independent entity to reduce
the opportunity for preferential treatment by the transmission provider.
7. More broadly,
the SMD Tariff must recognize the regional nature of today's energy
markets. Transmission capabilities must
be calculated not for a single utility's service territory, but regionally to
encompass existing trading patterns and power flows, particularly parallel path
flows on neighboring systems. All transmission
providers that are not part of a Commission-approved RTO must contract with an
independent entity to perform transmission capability calculations on a
regional basis. Likewise, we propose to
require a common OASIS for the region.
8. Competitive and
reliable regional power markets require adequate transmission infrastructure to
allow geographically broad supply choices and minimize the complications
created by loop flow. The recent DOE
National Grid Study documented the problems resulting from recent
under-investment in transmission infrastructure and identified a number of
causes. Among the causes were the lack
of regional planning and coordination of transmission needs and siting
issues.
9. Transmission
planning and expansion have generally been performed for a single control area
rather than on a regional basis. This
yields sub-optimal solutions, as individual transmission providers consider
power flows across a limited area and do not adequately consider entire markets. Parallel path flows that occur on
neighboring systems may make the construction of specific facilities less
cost-effective than a regional solution.
This effect can be properly considered by performing transmission
planning and expansion on a regional basis.
Moreover, facilities that, if constructed in one system would be the
optimal solution for a neighboring system, might never be considered under a
single control area-based planning model.
10. Implementation of Standard Market Design
will only increase the importance of examining these issues on a regional
basis. More open and transparent
markets will enable customers to purchase from distant suppliers, increasing
use of the grid. Locational marginal
prices that result from the spot markets operated by an Independent
Transmission Provider would signal to all market participants the value of
additional supply and demand response at particular locations. Based on these prices over time, market
participants will be able to decide whether additional investment – in
transmission or generation facilities or demand response – is warranted. The ability of individual market
participants to see the economics of possible solutions and make market-driven
decisions concerning the addition of infrastructure is the fundamental
mechanism that induces efficient investment under Standard Market Design. The policy relies primarily on a
"ground-up" planning process that encourages construction by private
companies yet also recognizes the need for of a regional evaluation process for
loop flow effects and cost-effectiveness
It is neutral with respect to the type of investment market participants
may make in response to these price signals.
However, due to loop flow, all system modifications would need to be
coordinated through a regional process and would have to meet any criteria
needed to maintain reliability and stability, and assure that existing customer
rights are not impaired.
11. Given
the need for transmission investment in much of the country and the time it
will take to implement Standard Market Design and for investors to observe and
respond to price signals, we propose that a regional planning process be
instituted within six months of the effective date of the Final Rule. This process should be designed to identify
beneficial transmission needed for both reliability and economic reasons to
support regional markets and reduce the effects of generation
concentration. The regional planning
process should allow the market to respond to those identified needs.
12. A
critical piece of the transmission planning process is state-level siting
decisions. We note a recent National
Governors' Association report that recommends Multi-State Entities to
facilitate regional transmission planning decisions.162
Multi-State Entities, along with an open regional planning process,
would preserve the states' role in siting decisions, while promoting regional
solutions. A Multi-State Entity could
be an important component of the regional planning process.
13. Certain
areas of the country and organizations already have proposals or processes to
consider regional planning or development of regional markets. Building off of these existing efforts will
help facilitate the development of a regional planning process in the near term. We emphasize that a planning area need not
coincide with the geographic area of a Commission-approved RTO or Independent
Transmission Provider required by this rule.
Also, because of the interrelationships between Canadian and US energy
markets, we encourage participation by Canadian entities and provincial
authorities in the regional planning process.
14. Current
processes such as the Committee on Regional Electric Power Cooperation in the
West provide for state and provincial advice in the planning across the entire
Western grid. Therefore, we propose to use the area covered by Western
Electricity Coordinating Council (WECC) that encompasses the geographic area
covered by the Western Grid for regional planning purposes.
15. In
the Eastern Interconnection there have been several efforts at developing
regional wholesale electricity markets that we propose to build on for the
regional planning process. PJM and MISO
developed a Memorandum of Cooperation dated May 9, 2002 that commits to develop
a joint and common wholesale electric market for PJM, MISO, and SPP. Consequently, we propose that the area
covered by these organizations would also be a regional planning area.
16.
Similarly, New York ISO and ISO-New England are currently pursuing
discussions on the merger of these two organizations into a Northeast RTO. Both are also members of the Northeast Power
Coordinating Council which has recently conducted studies of transmission needs
in the region.163 We propose to build on
these efforts and use the area covered by these organizations as a planning
area.
17. Finally,
we recognize that there has been ongoing discussion development of regional
markets in the Southeast. SETrans
Regional Transmission Organization proposes to encompass a broad area in the
Southeast. The Tennessee Valley
Authority (TVA) has signed a Memorandum of Understanding with Southern
Companies and Entergy, two sponsors of SETrans, to work together to develop
coordination agreements. Additionally,
the SETrans and GridSouth Transco, LLC parties signed a Memorandum of
Understanding in January 2002 calling for similar regional coordination. Thus we propose to build on these efforts
and propose a Southeast planning area composed of the Southeastern Electric
Reliability Council and the Florida Reliability Coordinating Council.
18. We
propose that all public utilities that own, control, or operate transmission
facilities must participate in a regional planning process for the planning
areas discussed above. We propose that this
process start within six months after the effective date of the Final Rule and
that the first regional transmission plan be completed within twelve months
after the effective date of the Final Rule.
Reliance on these existing regional efforts should facilitate the
start-up of the regional planning process before Standard Market Design is
implemented and all areas have Independent Transmission Providers operating
transmission facilities.
19. After Standard Market Design is fully
implemented, we believe the regional planning process will change as
Independent Transmission Providers play a greater role in that process. There will still remain a significant need
for a regional planning process to supplement private "ground up"
investment decisions. The regional
planning process is intended to supplement these private investment decisions,
not supplant them. The regional
planning process must provide a review of all proposed projects to assess
whether the project would create loop flow issues that must be resolved on a
regional basis. In addition, because of
the externalities involved, there may be no private investment sponsor for some
projects that would benefit the region.
Private investment decisions in response to prices may not result in
adequate expansions for two reasons.
First, private parties may not be eligible to ask the state to exercise
its eminent domain rights. Second,
some needed and beneficial expansions may not create enough identifiable
financial benefits to compensate private investors adequately, so those
projects will not be built under a system that relies solely on private
investment to expand the grid. A
regional planning process can identify both the projects that would benefit the
planning area and potential alternatives in a fair and unbiased manner. Additionally, a regional planning process,
would evaluate the benefits of alternative proposals and provide an independent
assessment of which projects are the most cost effective and/or have the least
environmental impact.
20. To
complement private investment initiatives, we propose that Independent
Transmission Providers establish a mechanism for regional transmission planning
and expansion guided by the following principles. First, the planning process should identify all expansion needs
on the system, including both reliability and economic needs (e.g., to
reduce congestion). The planning
process should leave open the question of how and by whom those needs should be
met, without favoring one solution (whether it is transmission, generation or
demand response) over another. The planning process should be open to all
industry segments. Additionally, all
entities could propose projects. As
long as the project did not make existing Congestion Revenue Rights infeasible
due to loop flow problems, the entity would be free to complete the project as
long as it is willing to assume any market or regulatory risk. However, to the
extent the entity sought to roll-in the costs of the facilities, the rate
treatment should be reviewed through the planning process.
21. Second,
an Independent Transmission Provider should have the responsibility to issue
requests for proposals when the planning process determines that additional
resources are needed to serve the regional market. Parties may respond with proposals to expand the grid, add
generation (including distributed generation), or implement demand response.164
The Independent Transmission Provider would approve transmission
expansions that would be paid for by all customers only when planned private
investments are judged to be inadequate to meet the reliability and market
needs of the region. If the bidding
process fails to produce a satisfactory outcome, such that the Independent
Transmission Provider determines that additional facilities are needed, the
affected transmission owner(s) would be required to expand or upgrade the
transmission system.165
22. Finally,
the Independent Transmission Provider would act as a clearinghouse for proposed
projects. It could identify separate
projects that could be constructed at a lower cost if the projects were
combined. Also, if there are
alternative projects that have been proposed, the Independent Transmission
Provider could evaluate the relative advantages of the alternative
projects.
23. This
approach to regional planning and expansion is fully consistent with Standard
Market Design's goal of inducing efficient investment by relying primarily on
price signals and independently administered Congestion Revenue Rights. At the same time, it recognizes that private
investment decisions may not be fully adequate in all cases because of eminent
domain and the possibility that private benefits of investment could be
significantly less than social benefits.
The planning process would have a regional scope, permit direct
competition among all types of investment, include all market participants
equally, and minimize the need to rely on eminent domain and the support of
captive customers. Because existing
transmission owners are the transmission builder of last resort, it also
respects the reality that not all states allow non-traditional utilities to
build in their state or to obtain eminent domain, thus creating a legal barrier
to entry.
5. Transmission Facilities That Must be
Under the Control
of an Independent Transmission Provider
24. In
a variety of public forums, including RTO conferences and comments to RTO
proceedings, much uncertainty has been expressed concerning two questions: which facilities belong under the control of
the RTO; and which customer-owned transmission facilities that are turned over
to RTO control are entitled to a credit?167
In some instances, the dispute centers on whether the facilities are
integrated. Other disputes involve the
voltage level at which a facility is determined to be transmission. Under this proposed rule, the question
becomes which transmission facilities must be under the control or an
Independent Transmission Provider, be it an RTO or not.
a. Before Order No. 888
25. Before
Order No. 888, much of the industry consisted of vertically integrated
investor-owned utilities (IOUs) that, for the most part, provided a single
service – bundled requirements power – to retail and wholesale customers
alike. The classification of delivery
facilities between transmission and distribution came up only in a ratemaking
context. Because wholesale requirements
customers purchased bulk power, they often did not require service over
distribution facilities. Often, only a
stepdown substation or a feeder line was involved. For those few stand-alone transmission services that an IOU might
provide, the cost allocation issue was the same. The Commission approached this allocation issue by defining an
integrated transmission grid as those facilities that operate in a single cohesive
fashion to deliver bulk power and allocating wholesale (and stand-alone
transmission customers) a proportional share of the embedded costs of those
facilities on a rolled-in basis with postage stamp pricing.
26. Infrequently,
the Commission would consider rate treatments premised on the distinction
between transmission and subtransmission (high and low voltage
transmission). If there were delivery
facilities (transmission or distribution) that were not part of the integrated
grid, but were used by a specific wholesale customer (e.g., radial tap
line or stepdown substation), the Commission would allow the direct assignment
of those facility costs in wholesale rates.
27. These
issues were discussed at length in Commission cases in the 1970s when IOUs attempted
to bifurcate the pricing (effectively pancaking) and thereby increase their
wholesale revenues. Customers, on the
other hand, wanted to classify facilities as transmission and thereby decrease
their delivered energy charges by only paying one charge for these
facilities. While the issue was often
framed as a transmission/distribution issue, it was mostly a battle over
utilities trying to pancake rates (through charging a rolled-in rate plus a
direct assignment charge) for transmission facilities or facilities that
provided both transmission and distribution functions (dual-function
facilities).
b. Order No. 888
28. Order
No. 888 did not require a change in traditional rate treatments. However, since the Commission issued its
open access rules, a number of utilities have proposed subclassifications of
transmission, e.g., transmission and subtransmission. Protestors (generally transmission-dependent
utilities) have argued that this rate treatment favors transmission users that
are connected to the transmission system at higher voltages (i.e., the
transmission owners' own generation) by reducing their rates for open access
transmission service (because they pay only the high-voltage charge) and that
reclassification is just another way to pancake rates and increase charges to
low-voltage users. During the
Commission's public outreach, commenters pointed to such splits as the pool
transmission facilities (PTF)/non-pool transmission facilities in ISO New
England as an example. This is not a
consistent classification of pool transmission facilities and non-pool
transmission facilities among transmission owners in New England. A generator located on a lower voltage
portion of the ISO's grid must pay an additional non-PTF charge to access the
New England market, but other,
generators do not, putting the first generator at a competitive
disadvantage.
29. The
issue of transmission/distribution classification in Order No. 888 was in the
context of unbundled retail transmission service and the Federal Power Act's
legal jurisdiction distinction between "transmission" facilities
(subject to Commission jurisdiction) and "local distribution"
facilities (subject to state or local jurisdiction). To determine what facilities would be under Commission
jurisdiction for purposes of the Order No. 888 open access requirements and
what facilities would remain subject to state jurisdiction for purposes of
retail stranded cost adders or other retail regulatory purposes, the Commission
developed a seven factor test to determine what facilities are transmission
facilities and what facilities are local distribution facilities.168
With respect to the seven factor test, the Commission also stated that
it would defer to the state commission’s findings as to what facilities
constitute local distribution facilities if the state's determination was
consistent with our comparability principles.
In addition, dual purpose facilities, i.e., those used both for
transmission or wholesale sales and for local distribution, would fall under
the Commission's jurisdiction. To the
extent use of particular facilities changed over time, the Commission would
revisit these determinations. The
Supreme Court upheld these determinations upon appellate review.169
c. Test for Transmission Facilities
30. Order
No. 888's seven factor test was designed to determine the local distribution
component of an unbundled retail sale.
The test did not exist prior to Order No. 888 and in fact was created to
do something the Commission had never done before – identify local (retail)
distribution facilities. Thus, the test
identifies all facilities that are not local distribution facilities. We propose that this is the appropriate
starting point for determining which facilities belong under the control of an
Independent Transmission Provider. To
the extent that a transmission owner or Independent Transmission Provider
believes that certain facilities should not be under the Independent
Transmission Provider's control, the Independent Transmission Provider may
request an exception to this presumptive determination.
31. This
proposed test focuses on the presumption that, if a facility is transmission,
it belongs under the control of the Independent Transmission Provider. Thus, once a determination is made with the
seven factor test, there would be no need for an additional review under the
Commission's previous integrated facilities test. In MidAmerican Energy Company,170 the Commission explained that the
Commission's determination of which facilities are transmission is fluid and
dependent on actual the use of the facilities:
Although
we are accepting the state commissions' classification, we reiterate our
finding in Order No. 888 that to the extent that any facilities, regardless of
their original nominal classification, in fact, prove to be used by public
utilities to provide transmission service in interstate commerce in order to
deliver power and energy to wholesale purchasers, such facilities become subject
to this Commission's jurisdiction and review.171
In addition, the rates, terms and conditions of all wholesale and
unbundled retail transmission service provided by public utilities in
interstate commerce are subject to this Commission's jurisdiction and review.172
Further, our deference in this proceeding
does not affect the Commission's separate determination of what facilities must
be under the operational control of RTOs, including ISOs and Transcos.173 The Commission will make
this latter determination, taking into account the seven factors formulated for
purposes of determining jurisdiction as set forth in Order No. 888,174 the ISO principles set forth in Order No. 888,175 and the principles set forth in the RTO Final Rule.176
We note that the determination of which
facilities are under the operational control of the Independent Transmission
Provider does not dictate transmission pricing.177
We request comment whether, either in addition to or in lieu of the seven factor test, the Commission should use a bright line voltage test (e.g., 69 kV) to determine which facilities are placed under the control of the Independent Transmission Provider. If so, we seek comment on the bright line, whether we should allow regional variation, and how transmission facilities that are not placed under the control of the Independent Transmission Provider's tariff are treated with respect to open access and rates.
160To the extent that an Independent Transmission Provider’s load ratio share access charge calculation does not pick up this reservation, the amount of interface capability can be imputed and added to the customer’s peak day amount.
161See Section III and Appendix C.
162See Interstate Strategies for Transmission Planning and Expansion, National Governors' Association, posted on July 18, 2002, available in <http://www.nga.org/center/divisions/1,1188,C_ISSUE_BRIEF^D_4110,0.html>.
163Northeast Power Coordinating Council Collaborative Planning Initiative Phase I issued March 13, 2002.
164We recognize that the states have the ultimate authority over siting.
165See existing pro forma tariff §§ 13.5 and 15.4 (transmission provider required to expand its transmission system if transmission customer agrees to compensate the transmission provider). This requirement extends to the transmission owners.
167See, e.g., City of Vernon, California, 93 FERC ¶ 61,103 (2000), 94 FERC ¶ 61,344 and 61,148 (2001); 95 FERC ¶ 61,274 (2001); and 96 FERC ¶ 61,312 (2001).
168 Order 888 at 31,771.
169 New York v. FERC, 122 S. Ct. 1012.
17090 FERC ¶ 61,105 (2000).
171In Order No. 888, the Commission explained that "a public utility's facilities used to deliver electric energy to a wholesale purchaser, whether labeled "transmission," "distribution," or "local distribution," are subject to the Commission's exclusive jurisdiction under sections 205 and 206 of the FPA." Order No. 888 at 31,969; accord Nevada Power Company, 88 FERC ¶ 61,234 at 61,768 (1999).
172Transmission service in interstate commerce by public utilities, including the rates, terms and conditions for such service, remains within this Commission's exclusive jurisdiction. 16 U.S.C. 824, 824d, 824e (1994). See generally Order No. 888_A at 30,339_41.
173Which facilities will or will not be under an RTO's operational control also does not predetermine transmission pricing, cost allocation, or rate design determinations at either a state commission or at this Commission.
174Order No. 888 at 31,771.
175Order No. 888 at 31,730_32.
176Regional Transmission Organizations, Order No. 2000, FERC Stats. & Regs. ¶ (1999) (RTO Final Rule).
177As noted in MidAmerican, present ISO agreements obligate transmission owners to provide access over facilities that are not under the control of the ISO if those facilities are needed to provide wholesale transmission service regardless of ownership or whether those facilities are labeled transmission, distribution (i.e., distribution facilities other than local distribution), or local distribution. The same holds for Independent Transmission Providers.