III.       NEED FOR REFORM

            A.            Undue Discrimination and Impediments to Competition Remain

1.         Since the issuance of Order Nos. 888 and 2000, it has become clear that additional, mandatory measures are needed to achieve the goals of non-discriminatory transmission access and competition in electricity markets.  Vertically integrated transmission owners and operators continue to use their interstate transmission facilities in ways that inhibit competition in wholesale power markets as well as competition in those retail power markets where states have adopted retail choice.  The discriminatory preferences that these transmission owners and operators give to their own uses of the interstate transmission grid to serve their retail customers (whether or not they are in retail choice states) results in discrimination against, and in costs being borne by, other wholesale and retail customers who also rely on the interstate transmission facilities to buy power.  The discriminatory preferences also create barriers to new sellers that could provide lower-cost power.  This could result in higher prices to the native load served by the transmission owner.  For example, transmission-dependent utilities30 and other load-serving entities need the interstate transmission facilities to move power they are purchasing by contract from distant generators or suppliers, but allege that despite the requirements of Order No. 888, they are denied comparable access to the grid.  Similarly, new generators wishing to compete in wholesale markets or for retail customers in retail choice states tell us that they are denied comparable access to the grid, thus inhibiting entry of new, lower-cost, efficient and environmentally superior power suppliers.

2.         The Commission recently has taken additional steps to address some of the remaining impediments to non-discriminatory transmission access and competition in wholesale power markets.  For example, the Commission's recently issued Generator Interconnection proposed rule seeks to remove one particular type of undue discrimination occurring in the marketplace – barriers to obtaining interconnections to the interstate transmission grid – so that new generators can compete with vertically integrated transmission providers to serve load.31  However, this initiative will resolve only one aspect of remaining discriminatory practices.  Other opportunities for vertically integrated transmission providers to operate in ways that favor their own generation remain within the construct of the pro forma tariff (e.g., preferences for native load and network customers to reserve transmission capability, differing transmission services that raise barriers to competition, the lack of inclusion of all services under the same tariff).  As noted in Order No. 2000, "perceptions of discrimination are significant impediments to competitive markets.  Efficient and competitive markets will develop only if market participants have confidence that the system is administered fairly."32

3.             Furthermore, it has become apparent that there are also opportunities to discriminate and to hinder an efficient, competitive marketplace due to the absence of standardization with respect to market rules and practices within and between regional markets.  So-called "seams" problems (e.g., different rules and different pricing systems)  create transaction costs and artificial barriers to trade.  These problems inhibit the Commission from fulfilling its statutory responsibility to ensure that customers receive reliable power supplies at the lowest reasonable costs.33

4.             Finally, innovation that the Commission expected to see with respect to new service offerings has been sporadic and unsteady.  Innovations in transmission control and pricing (e.g., ISO control of transmission and LMP for generation and transmission services in the Northeast, RTO formation in the Midwest), while impressive, have been slow to take root in other regions of the country.  The pro forma tariff was envisioned as the baseline above which transmission providers were encouraged to develop competitive and customer-responsive service offerings.  But Florida Power Corporation's network contract demand service, a hybrid of Network Integration Transmission Service and Point-to-Point Transmission Service features,34 and Duke Energy Corporation's "recallable long-term firm" service35 are the only noteworthy new services accepted by the Commission for use with a single utility's open access transmission tariff.  Other proposed pro forma tariff revisions amounted to little more than working around the edges of the existing services and procedures and did not produce more competitive transmission service that reduces overall electricity costs. 

5.         Most ISOs recently introduced centralized short-term real-time hourly markets and day-ahead markets for energy (i.e., spot markets) where sellers sell into the market and buyers buy from the market without matching a particular seller with a particular buyer.  In such organized spot markets, there is a single market clearing price established that is received by all generators who bid into the market below that price and is paid by all load that bids in above that price.  However, the ability of customers to bid demand reductions into the spot market in response to supplier prices is still limited and needs to be improved significantly for short-term markets to operate more competitively.  Further, while there have been benefits of market development in the Northeast (PJM, New York ISO, ISO-New England), Texas and California (during the first two years of its restructuring), the Midwest ISO is still in the formative stages of operation with respect to markets, and few market benefits have materialized in the Southeast and West.

B.            Specific Instances of Undue Discrimination and Impediments to Competition

 

6.         The specific reasons for requiring reform are many.  Market participants have identified, through formal complaints, hotline calls, public conferences, and pleadings, the difficulties they have experienced in gaining equal access to the transmission grid to compete with vertically integrated utilities to serve load.  Much of this problem is directly attributable to the remaining ability of such vertically integrated utilities (and the existence of sufficient incentives) to exercise some degree of transmission market power in order to protect their own generation market share.  Further complicating transmission access is the fact that not all transmission service is provided under the rates, terms and conditions of the Commission's pro forma tariff.  Rather, over 60 percent of load has been subject to various state rules governing the transmission component of bundled retail transactions.  Independent transmission service under a common set of rules would solve many of these problems.

7.             Nevertheless, new problems have been created by some of the market design experiments.  In regions of the country where the separation of transmission from generation has been addressed through the creation of ISOs (which, in some instances, have placed nearly all load under a single tariff), market design flaws create inefficiencies in the marketplace and opportunities for the exercise of market power.  Conflicting market rules and procedures in neighboring ISOs have created or perpetuated seams problems that impede the economic flow of power from one region to another.  All of these problems have hindered the progress towards competitive regional electricity markets.  Standard Market Design is intended to address these problems.

1.            Transmission Market Power by Utilities that are Not Independent

8.         By differing means, Order Nos. 888 and 2000 attempt to effect open access transmission by reducing the ability of transmission owners that also own generators to act in anticompetitive or unduly discriminatory ways against other generators.  In both orders, the Commission attempted to move the electric industry into a competitive wholesale market without mandating corporate restructuring.  Through Order Nos. 888 and 2000, the Commission required open access to public utility transmission systems, encouraged the formation of ISOs and, later, RTOs to achieve control of the transmission grid by entities that are independent from generation marketing or sales.  However, only limited portions of the country have moved beyond the basic requirements of open access (e.g., through the voluntary divestiture of generation or establishment of RTOs, ISOs, or ITCs).  In the rest of the country, the remaining corporate ties between generation and transmission within public utilities have proven problematic for transmission access.  Thus, across most of the nation, barriers to entry remain for new generators and new load-serving entities.

9.         A large portion of this problem is directly attributable to the continued ability of vertically integrated transmission providers to exercise some degree of transmission market power to advantage their own or affiliated generation.  The longer the vertically integrated transmission provider can use access to interconnection or transmission service to delay or prevent entry of competing generators to its service territory, the longer it can profit from its own generation sales with a limited threat of competition.  Vertically integrated transmission providers have found numerous ways to delay or prevent entry of competitors, some within the existing rules and some by exceeding reasonable discretion afforded to the transmission provider.  All of these are difficult to monitor or prevent with behavioral rules.36                       

10.       As part of Standard Market Design, we propose that an Independent Transmission Provider operate all transmission facilities.  The requirement for independent control of the transmission grid, preferably by an RTO, resolves these types of problems.

                                    a.            Load Growth

11.       Under the current pro forma tariff, a transmission provider is required to plan its system to allow customers with existing long-term contracts to extend, or roll over, those contracts.37  However, the transmission provider has a right to recall that transmission capacity if it identified in the initial agreement with the customer that it had projected native load growth that would require that transmission capacity.38  Transmission providers have failed to identify any native load growth at the time of the initial agreement, and disputes have arisen with customers claiming they were denied the ability to roll over their contracts because the transmission provider claimed, well after the contract was executed, that the transmission capacity at issue was required to serve native load growth.39

12.       In Standard Market Design, we propose to eliminate the preference for future native load growth.  Instead, since Congestion Revenue Rights will be used to assure price certainty, Congestion Revenue Rights will be apportioned based on historical use or by an auction, neither of which grants preference for future load growth by a particular supplier; this approach resolves these concerns.

                                    b.              Delays in Responding to Requests for Service

13.             Another type of anticompetitive behavior centers on a vertically integrated transmission provider delaying the processing of a competitor's request for new transmission service or interconnection (including the related system impact or facilities studies).  Transmission providers have done so by failing to follow time lines or expansively interpreting the tariff procedures.  These delays may be enough to cause the competing generator to lose the sale, particularly if the potential customer is concerned that it may lose service completely if it does not stay with the transmission provider.40

14.       Under Standard Market Design, these types of delays are resolved through the requirement for an independent entity, preferably an RTO, to perform studies and calculate available transfer capability (ATC),41 since an independent entity would have no incentive to favor one customer over another.

                                    c.            Scheduling Advantages

15.       A vertically integrated transmission provider has a structural advantage over many competitors to make economy sales or to serve its own load, primarily because it has a large portfolio of both generators and loads.  A competitor with access only to generation outside of the control area and no native load has to identify the delivery point of its power before being able to secure transmission service.  But a vertically integrated transmission provider does not have to identify a specific location on the grid to serve its load because its load is dispersed across its entire system.  A vertically integrated transmission provider also does not have to identify a single generation location, but can run a combination of its own generators or purchase from lower cost-suppliers inside or outside of its system.  It can schedule purchased power to one of its own loads (in place of power from one of its own generators) in order to secure transmission service for the purchase.  Later, it can find a buyer for the power and schedule transmission service from one of its internal generators to the load.  This often is enough of a scheduling advantage over a competing supplier to ensure that the transmission provider (or its affiliated power marketer) gets the sale.

16.       While it is true that all network customers have these same rights and abilities, in many areas of the country the only customer using network service is the vertically integrated transmission provider.  Moreover, the vertically integrated transmission provider's size of resources and loads is usually much greater than any other network customer, giving it that much more of an advantage in flexibility.  In addition, the vertically integrated transmission provider may have an advantage through access to better or more transmission and other related information.

17.       Under Standard Market Design, all transmission service will be provided under a new Network Access Service.  Having one service for all customers will eliminate scheduling advantages of competing suppliers.

                                    d.            Imbalance Resolution

18.             Customers have also alleged that vertically integrated transmission providers have an advantage over competitors in the resolution of energy imbalances.  Transmission providers with generation and load of their own can resolve their own energy imbalances through in-kind energy exchanges with neighboring systems.  In contrast, other customers of the transmission provider face higher costs if they take service from other suppliers that could balance against each other.  This difference gives the transmission provider a competitive advantage over other sellers of power.

19.       Under Standard Market Design, all suppliers and loads on a system will resolve imbalances through the same energy imbalance procedures.  This will remove any competitive advantage the transmission owner with its own generation and load may have over competing power suppliers.

                                    e.            Available Transfer Capability and Affiliates

20.             Another source of discrimination is the calculation of Available Transfer Capability.  A transmission provider that is not independent calculates its Available Transfer Capability, using its own proprietary data and its own equations.  This discretion gives it the ability and the opportunity to discriminate in its own favor against entities that rely upon the OASIS for Available Transfer Capability information.  In several cases, the Commission has found that utilities' OASIS postings reflect an inaccurate Available Transfer Capability.  Indeed, in response to "serious concerns about the integrity of the postings of ATC" on the OASIS systems of two transmission providers, the Commission required the transmission providers to employ an independent third party to administer their OASIS systems.42

21.       Under Standard Market Design, an independent entity will calculate Available Transfer Capability and schedule transmission service.  This will eliminate this potential for undue discrimination.

                                    f.            OASIS Postings

22.             Manipulation or violation of OASIS posting requirements and the Commission's standards of conduct is another way vertically integrated transmission providers that control their own OASIS sites are able to engage in undue discrimination.  This can occur through prohibited off-OASIS communications between the transmission provider and its affiliated market participant, e.g., informing only the affiliate about Available Transfer Capability that will soon become available and posted on the OASIS so that the affiliate will be first in line to claim the capability.43   Such abuses reinforce our belief that, in the absence of an independent entity calculating Available Transfer Capability and operating a transmission provider’s OASIS, "a transmission provider's self-monitoring of its standards of conduct is not sufficient, and that it is essential for interested parties to be able to participate in this process" of reviewing communications between market participants.44  Further, even with the best of intentions, it is not possible for a single transmission provider in a region to calculate Available Transfer Capability on its system alone without accounting for the transactions over all the other systems in its region and neighboring regions.

23.             Similarly, control over the design, function and maintenance of OASIS systems may also present opportunities for discrimination.  The Commission has been concerned for some time that transmission providers have the ability to impede competition by making their OASIS sites difficult to use, limiting users' access to OASIS and limiting access to information about transmission curtailments and interruptions that would allow the Commission to identify instances of undue discrimination.45

24.       Under Standard Market Design, an independent entity will operate an OASIS on a regional basis, and thus will remove any advantages one seller may have over another and improve the accuracy of regional Available Transfer Capability postings on the OASIS.

                                    g.            Capacity Benefit Margin Manipulation

25.       The Commission has found instances of transmission providers taking advantage of their ability to reserve interface capability to serve their own load while limiting the ability of competing suppliers to access customers on its system.  For instance, transmission providers have reserved excessive amounts of capacity benefit margin (CBM) to serve their own load,46 and violated the pro forma tariff by reserving large amounts (e.g., 2,000 MW) of transfer capability at multiple interfaces, under the label of "firm import for native load," without designating resources or loads associated with the reservations as other transmission customers are required to do.47  Import capability reserved by the transmission provider blocks a competing supplier from securing firm service across the interface, limiting that supplier’s ability to compete to serve load on the system, or on neighboring systems.  A related issue is whether those who set aside transmission for CBM are reserving it and paying for it under the terms of the pro forma tariff.  When transfer capability for CBM is set aside for the use of one market participant, its cost is not necessarily allocated to that market participant alone.  Because transmission facility embedded costs are allocated to transmission customers on the basis of use – capacity reservation for Point-to-Point Transmission Service customers and load ratio share (which does not include the transmission capability set-aside of CBM) for Network Integration Transmission Service customers –  all customers may unfairly subsidize the cost of the CBM capability. 

26.       Under Standard Market Design, entities that want to reserve transfer capability must pay for that capability to reach generation reserves across an interface.  Thus, the preferential treatment would be eliminated.

                                    h.            Discretionary Use of Transmission Loading Relief

27.       The opportunity for anticompetitive behavior arises when transmission providers have discretion to dispatch their own generation to serve their own load in a way that requires transmission service curtailments through the use of transmission loading relief (TLR) procedures. 

28.       There has been a sharp increase in the number of TLRs used in some regions, suggesting that transmission operators rely upon them to do more than simply relieve emergency transmission overloads.48  There are unmistakable financial incentives to rely on TLRs in forward transmission planning:

The increased incidence of TLRs may suggest that some transmission capacity is being oversold.  Market participants have attributed a tendency to implement a greater number of TLRs to the commercial reality that transmission providers do not have to refund transmission reservation fees for service curtailed because a TLR is called.[49]

 

29.       When a vertically integrated transmission provider injects power from its own generation onto its own power lines to meet the constantly shifting demands of the load on its system, it has both the opportunity and the incentive to manipulate the transmission system for its own benefit.  It can either dispatch generators to create a transmission constraint that prevents a competitor from making a sale that the transmission provider would also like to make, or it can capitalize on legitimate constraints into a load pocket to curtail a competitor's transmission transaction and serve the customer with its own generation instead.  The key here is that none of the transmission provider’s actions require direct communication with its merchant function or marketing affiliate.  A simplified hypothetical example of such anti-competitive behavior is set forth in Appendix C.

30.             Several aspects of our proposed remedy address this concern, including the use of LMP to manage congestion and the requirement that transmission facilities be operated by an Independent Transmission Provider.

2.            Lack of Common Rules Governing Transmission

31.       Some of the difficulties that come from having different rules as power moves across the grid are discussed later in the Seams Problems Section III.B.4), where a "seam" is a dividing line between different sets of grid rules.

32.       Having two or more different sets of rules governing the operation of a transmission system makes it difficult – if not at times impossible – for that system to support an efficient regional electric power market.  If the interstate transmission system is to provide fair and efficient movement of power on behalf of all users of the system, the same general rules must govern such matters as who gets service, who has the right to transmission service when not all service requests can be accepted, how the transmission facility costs are allocated among transmission customers, who gets its transmission curtailed and by how much when a transmission outage prevents all the planned services from being accommodated, who plans the additions to the grid and who pays for these additions. 

33.       Today there are not only different rules in different public utility systems, but there may be more than one set of rules for transmission owned by a single utility.  This is because there are different rules for two types of wholesale transmission service, and the rules for bundled retail transmission service may differ from the rules for wholesale and unbundled retail transmission services.

34.       The Commission established an open access transmission tariff under Order No. 888 that provides for two distinct types of wholesale transmission services – Network Integration Transmission Service and Point-to-Point Transmission Service.  Network Integration Transmission Service was designed primarily to meet the needs of the transmission customer that wants to integrate many generators and many loads at diverse locations on the public utility's grid; it was intended to be comparable to the service that the public utility provided to its own bundled retail customers.  Point-to-Point Transmission Service, as the name implies, was designed primarily for the customer that wants to move power from one discrete location to another.

35.       At the time Order No. 888 issued, the Commission recognized the potential for problems with having two wholesale services that could not be truly equal, especially the problem of dealing with claims of undue discrimination between the services.  Consequently, along with the issuance of Order No. 888 the Commission proposed a rule to create a new tariff, called the Capacity Reservation Tariff.50  It was intended to remedy the anticipated problems by establishing a new tariff that would replace the two wholesale services with one.  The Commission received many comments on the proposed rule and held a technical conference with representatives of diverse stakeholders.51          

36.       Some parties expressed concern about moving quickly to a single service based on the Capacity Reservation Tariff model, while other parties asserted that, although a single tariff reducing the two services to one was a good policy, there were problems with the particular Capacity Reservation Tariff that was proposed.  They recommended that the Commission delay acting on the proposed rule until it learned the best form of single service tariff through industry experience with open access.  This is the approach that the Commission in effect followed.  Since the two Order No. 888 services were adopted, however, there have been allegations of undue discrimination between customers of the two services as discussed later in this section.

37.       There are also different rules for bundled retail transmission service and for wholesale and unbundled retail transmission services.  States have historically established the rules for the transmission component of bundled retail transactions, while the Commission has established the rules for wholesale and unbundled retail transmission services.

38.             Despite the requirement in Order No. 888 that no transmission customer may have any undue advantage over another, there remain real or perceived advantages for the customers of vertically integrated transmission owners.  In many cases, the perceived advantage is one of Network Integration Transmission Service over Point-to-Point Transmission Service, where Network Integration Transmission Service is available to both bundled retail transmission customers and wholesale Network Integration Transmission Service customers, while Point-to-Point Transmission Service is taken primarily for wholesale transmission by independent power producers and marketers.

39.       Four prominent examples highlight the alleged advantages that a public utility's bundled retail customers have over wholesale and unbundled retail customers.  First, certain reliability practices related to keeping the transmission system balanced may allow a public utility that is responsible for keeping generation and load in balance to obtain lower costs for its own power customers.  Second, a transmission-owning public utility may have more de facto flexibility to designate transmission receipt and delivery points than other transmission customers, if that public utility also provides power to customers on its transmission system.  Third, the bundled retail customers of a transmission owner may have certain transmission reservation and pricing advantages regarding transmission transfer capability set aside for reliability.  Fourth, state transmission curtailment rules that favor a public utility's bundled retail customers may conflict with the Commission's transmission curtailment rules, resulting in a transmission preference to customers in one state over customers served in other states.52  The first three of these were summarized above, and a detailed discussion with examples is set forth in Appendix C.

40.       The requirement for all services on the transmission grid to be taken under a common set of rates, terms and conditions will resolve these concerns.

3.            Congestion Management

41.       Due to new transmission usage patterns and the lack of transmission infrastructure improvements, congestion has increased.  However, economically sound congestion management plans do not exist in most parts of the country, and transmission customers have been exposed to transmission service interruptions and increasing generation costs due to the risk of interruption.  The operating rules that do exist were not designed as a congestion management tool for allocating scarce transmission capacity, but were designed to keep facilities from overloading in an emergency, such as when a transmission facility unexpectedly goes out of service.

42.             Currently, under the existing pro forma tariff, congestion is managed primarily through a system of physical reservation of capacity, based on each individual transmission provider's calculation of the Available Transfer Capability of its grid, a calculation often made without knowledge of the power flows on its grid that result from transactions scheduled over other grids in its region.  Under the current pro forma tariff, customers reserve capacity on either a firm or non-firm basis, based on the assumed contract path that the transaction will use.  Once the customer has reserved capacity on a firm basis, it is supposed to receive certainty both that power will be delivered and the price that the customer will be charged for transmission.  If the customer has non-firm capacity, it has no certainty that capacity will be available to deliver power, but does know that there will be no congestion charge if the delivery does occur.

43.       The existing pro forma tariff also provides that the redispatch of a transmission provider's generating units to relieve congestion is required only if it can be achieved while maintaining reliable operation of the transmission system in accordance with prudent utility practice.  The recovery of the higher generation costs resulting from such generator redispatch, which are a subset of opportunity costs, requires that (1) a formal generator redispatch protocol be developed and made available to all transmission customers and (2) all information to calculate redispatch costs be made available to the customer for audit.  If a transmission provider collects revenues to cover the redispatch costs from a specific transmission customer, it must credit these revenues to the cost of fuel and purchased power expense included in its wholesale fuel adjustment clause.  Various tariff provisions specify how redispatch is to be implemented.  For instance, Sections 33.2 and 33.3 of the existing pro forma tariff provide that the redispatch of all network resources and the transmission provider's own resources, on a least-cost basis without regard to ownership, is to be performed only to maintain system reliability, not for economic reasons.  Under those circumstances, the redispatch costs would be shared among the network customers and the transmission provider on a load ratio basis.  Sections 13.5 and 27 of the existing pro forma tariff permit the transmission provider to provide the requested transmission service and relieve a system constraint by redispatching the transmission provider's resources:  (1) if this costs less than constructing network upgrades; and (2) if, under Section 13.5, the transmission customer agrees to compensate the transmission provider for any such redispatch costs on an incremental basis as specified in the customer's service agreement prior to the commencement of service.

44.             Although the existing pro forma tariff allows the recovery of generating unit redispatch costs, the Commission generally has not accepted proposals submitted by single-utility transmission providers to recover such costs.  For instance, the Commission rejected Bangor Hydro-Electric Company's (Bangor Hydro) proposed formula to recover opportunity costs for lack of supporting data showing that its opportunity cost pricing would be consistent with the principle of comparability and because the formula lacked sufficient detail to operate as a rate formula itself.53  The Commission directed Bangor Hydro to submit a separate section 205 filing with revised opportunity cost pricing before implementing such pricing.  The Commission also rejected a proposal by the operating companies of Central and South West Corporation (CSW) regarding redispatch costs because they did not provide sufficient specificity to enable a customer to calculate or verify redispatch costs and because the formula lacked sufficient detail to operate as a formula rate.54  The Commission also directed CSW to submit a separate filing under section 205 before implementing such pricing.

45.             Because it is difficult for a single-utility transmission provider to develop a formula that specifies the costs of redispatch and protects transmission customers' interests, generation redispatch has not been used as extensively as it could be used to relieve congestion.  A transmission provider will not redispatch generating units if it cannot collect its higher generation costs, and less transmission transfer capability will be available to the energy market.

46.       In 1998, the Commission called on public utilities to work with the North American Electric Reliability Council (NERC) to develop a congestion management system based on redispatch.55  NERC responded with its pilot Market Redispatch program that relied on counterflow transactions, i.e., power transfers against the prevailing flows on the constraint, to relieve the congestion.56  Although the program has been in place for several years, it has been implemented only infrequently because of the difficulty in establishing counterflow transactions and the limited availability of data to the transmitting customer.57

47.       In 1998, Commonwealth Edison Company (ComEd) proposed a similar voluntary redispatch program, which predated NERC's Market Redispatch Program.58  In November 1998, ComEd submitted the first of two interim reports to the Commission summarizing its experience with the program.59  It determined that a single utility cannot effectively offer redispatch over other systems, especially where other generation owners do not participate.

48.       The overall result of the Order No. 888 congestion management system is that the transmission system is not utilized in the most efficient manner.  Customers can be denied access to lower-cost supplies that could be made available if the congestion management and pricing system had an efficient and fair method of recovering the cost of generator redispatch. 

49.             Managing congestion using an LMP system, coupled with a single transmission service that relies on price (rather than first-come, first-served) to allocate limited transmission capacity, will resolve these problems.

4.            Seams Problems

50.       A lack of common transmission rules inhibits competition in power markets not only when there are different rules for different customers under one public utility's tariff or one RTO's tariff, but also when there are different rules from one public utility to the next, or from one RTO to the next.  The term "seam" has come into common use in the electric power industry over the last several years to refer to a boundary between areas with different transmission or other market rules.  Market participants assert that it can be difficult to move power "across a seam" from one area to another.

51.       Seams issues include differences in transmission rules as well as differences in power market rules.  They include such diverse matters as different operating rules (e.g., rules for recalling firm transmission capacity; coordination of generation and transmission maintenance schedules; how parallel path flows are determined to affect other regions); different market rules (e.g., bidding rules; market product definitions); different market designs (e.g., congestion management procedures; demand response rules; market price intervention practices); different business practices (e.g., scheduling practices; reservation practices; OASIS designs; processes to verify transactions between ISOs and market participants; transmission and generation outage information dissemination, compensation, and coordination rules; generation interconnection practices; liability provisions); and different electronic and telephonic communications protocols.

52.             Market participants have called for a "seamless market," by which they mean a market whose operation is not encumbered by differences in rules at public utility or RTO boundaries.  To achieve a seamless market, some assert that rules may differ but only in ways that the differences are invisible to power sellers and buyers.  Others assert that such management of differences rarely works in practice and that the rules must be the same everywhere to achieve a seamless market.

53.       The Commission has long recognized the need for more coordination and uniformity throughout a region in transmission matters.  Our Regional Transmission Group Policy Statement of 199360 encouraged public utilities to develop a common set of rules for regional expansion planning, and our Transmission Pricing Policy Statement of 199461 encouraged the development of a common pricing policy for a region that would internalize and rationalize the pricing of parallel path flows.  As explained above, Order Nos. 888 and 2000 recognized the need to bring the various public utility transmission systems in a region under a common set of transmission rules.  Order No. 888 not only applied a common set of open access transmission rules to public utility transmission systems, but included a reciprocity provision that conditioned a non-public utility's use of a public utility's open access transmission tariff on the non-public utility's agreement to provide comparable transmission service to the public utility.  Indeed, Order No. 888 also encouraged the formation of ISOs not only to bring all the transmission systems in a region under common rules, but also under unified operation.  Many parties in Canada have stressed the necessity of having a common set of rules for reliability and trading protocols for cross-border transmission facilities.62  Order No. 2000 built on this theme by strongly encouraging the formation of RTOs to bring all facilities in a region under a common set of transmission rules.  However, RTOs have not developed at the pace anticipated when Order No. 2000 was issued and seams problems continue to exist.  In June 2001, the Commission held a technical conference on seams issues.63  Participants to the seams conference explained that resolution of seams issues is critical for making the inter-RTO transmission systems and power markets work.

54.       We set forth in Appendix C a number of examples of differences in rules that can create seams problems, and a discussion of efforts at the Commission or within the industry to address seams problems.

55.       The requirement under Standard Market Design for a single tariff and a single market design operating with the same set of rules throughout the entire interconnection resolves the seams problems discussed above.

5.            Market Design Flaws

56.       Poorly designed market rules, or market rules with unforeseen or unintended consequences, can have a debilitating effect on markets, market pricing and overall confidence in the markets of the market participants.  Moreover, differences in market designs in neighboring regions can also lead to problems such as the exercise of market power through the exploitation of the differences.

57.             Wholesale electricity markets are complex, with multiple products traded at multiple locations on different time-frames, while subject to the unique physical characteristics of electricity (e.g., non-storable, need for system stability and balancing, physics of power flows).  Market rules have been affected by the variation in generation mix, the transmission network layout and the local and regional regulatory history in different regions of the country.  For example, the initial California markets had a design quite different from the designs of the markets in the Northeast region (PJM, New York and New England).

58.       In the regions where voluntary, organized ISO markets for energy, transmission and ancillary services have been established under the existing tariff, problems due to the design choices have been characterized as "market design flaws."  A market design flaw is a market rule – including product specification, bid format, auction rules and pricing rules – that allows distortions in the market prices or availability of a product or service, whether energy, ancillary services, transmission service or installed capacity.  In the years since the ISO markets have been operating, dozens of market design flaws have been identified, ranging from minor problems that cause temporary inconveniences to major problems that require markets to be re-designed.  No region has been exempt from market design flaws of one type or another.  We set forth in Appendix C examples of specific design flaws.

59.       These problems have resulted in markets that are inefficient and do not produce the lowest reasonable prices for electric power.  These problems cannot be resolved on a case-by-case basis because that will maintain and exacerbate the problems due to local differences in rules.  Only standardization of electricity market design will solve these problems.  In the parts of the country in which markets are most mature, including the Northeast, Midwest and California, there is broad consensus on the principal elements of market design and business practices.  A standard market design rule will help advance this process and extend it to other regions.  Our goal is to use the Standard Market Design rulemaking to address and remedy many of the market design flaws identified to date and to raise the quality of all electric markets simultaneously.

60.             Market rules will need to be flexible and have the ability to evolve over time.  However, consistent rules across the entire interconnection based on best practices, coupled with sound market monitoring to promptly identify and correct any design flaws will provide the necessary foundation for future market innovation and improvement.

C.            Reform Essential Given the Changed Nature of the Electric Industry 

 

61.       The need to address the instances of discrimination described above is all the more critical given the changing nature of the electric industry.  The United States electric power industry is in the middle of a transition from a predominantly monopoly industry to a predominantly competitive industry.  The fundamental economic driver of change has been, and continues to be, the reduction of economies of scale in new generation construction, combined with environmental restrictions that encourage gas-fired units.  This is due in large part to the introduction during the 1980s of highly efficient gas turbines and combined cycle generators that produce much more electricity from a given amount of gas.  A relatively small gas-fired generator can compete effectively with power from a large central generating station.  Additionally, small distributed generation is becoming economic, and some renewable energy resources, especially wind power generation, are also on the verge of becoming competitive.64  In the right locations, wind generating units can compete with the much larger coal, nuclear and hydroelectric units.65

62.             Because of these fundamental changes in industry technology, small producers of electricity can compete with large producers, and both the smaller utilities and the retail customers of a number of utilities have demanded access to competing power suppliers in hopes of lowering their electric bills, improving service and harnessing new technologies.   The pressures for retail access have been greater in regions with higher rates, which are typically regions with few low-cost natural resources for generating electric power, such as nearby coal mines, gas fields, and hydroelectric areas.66  Many of these regions have taken the lead in retail restructuring, while regions with historically low electricity production costs have proceeded more cautiously or even affirmatively decided not to change their retail access policies or to support their local utilities' participation in regional programs at this time.67

63.       One hallmark of electric industry restructuring has been the growth of wholesale trade.  In the past, wholesale power purchases made up a small fraction of a large vertically integrated utility's power supply, with most of its power needs met by its own generation.  Today, however, even large vertically integrated utilities rely increasingly on wholesale purchases for their energy supplies.  For example, as shown in Table 1, between 1989 and 2000, generation by investor-owned utilities grew from 2,132 thousand GWh to 2,230 thousand GWh, an increase of less than 5 percent.  During this time, wholesale power purchases by these utilities almost tripled.  Table 1 also shows that in 1989 wholesale power purchases provided 18 percent of the total electric energy available to investor-owned utilities from both wholesale purchases and their own generation.  By 2000, wholesale purchases provided over 37 percent of investor-owned utility electric energy.  This percentage has steadily increased since 1989, and is expected to continue to grow as utility-owned plants are sold or retired and new power supplies are acquired competitively in most parts of the country.

Table 1.  Investor-Owned Utilities' Total Purchases, 1989 - 2000,

              As a Percentage of Energy Purchased and Self-Generated

 

                                                                                                                                   

Year

IOUs'

 Purchases

IOUs'

 Generation

           Purchases     

(Purchases + Generation)

 

(GWh)

 (GWh)

(%)

 

 

 

 

1989

460,627

2,132,065

17.8

1990

530,325

2,134,429

19.9

1991

635,015

2,145,435

22.8

1992

671,758

2,143,847

23.9

1993

718,876

2,216,724

24.5

1994

732,710

2,237,652

24.7

1995

786,676

2,269,958

25.7

1996

916,087

2,308,156

28.4

`1997

1,080,538

2,321,225

31.8

1998

1,073,638

2,402,571

30.9

1999

1,083,892

2,353,639

31.5

2000

1,324,558

2,229,617

37.3

 

 

 

 

]Source: RDI POWERDAT Database

Note: Data for 2001 is not yet available.  Investor-owned utility purchases include purchases from affiliates.

 

1.         Table 1 demonstrates the increasing importance of competitive wholesale energy acquisition in the United States electric power industry, and the need for this Commission to ensure that transmission, market rules and institutions are reformed as necessary to support the new environment.  It also makes clear that a retreat from competitive markets to a cost-regulated vertically integrated world would be difficult – the nation now depends increasingly on wholesale interstate electricity markets.

2.             Similar data are presented in Tables 2 and 3 for large public power utilities and generation and transmission cooperatives that generate at least some of their own power.68  These tables show that wholesale purchases, on average, provide about 40 percent of the power needs of these large utilities.  Data are not presented for the smaller public power and cooperative utilities because they typically do not self-generate but buy all of their power at wholesale.

 

Table 2.  Large Public Power Utilities' Total Purchases, 1992 - 2000,

              As a Percentage of Energy Purchased and Self-Generated

 

 

Year

Utilities'

 Purchases

Utilities'

 Generation

           Purchases     

(Purchases + Generation)

 

(GWh)

 (GWh)

(%)