F. Day-Ahead and
Real-Time Market Services
1. This section
sets forth the bidding, scheduling, price determination, and settlement
provisions necessary to implement LMP in the day-ahead and real-time markets
for energy, regulation and both operating reserves. In this section, we lay out the basic elements that would be used
for congestion management and operation of the spot markets.138
1. Design of the Day-Ahead Markets
2. We propose
that the Independent Transmission Provider operate day-ahead and real-time
markets for energy and certain ancillary services in conjunction with its
scheduling of transmission service day ahead and in real time. These markets would allocate transmission
and generation capacity among competing uses in different markets through LMP
pricing. For example, the markets would
determine how much transmission capacity would be allocated for transmission
service to market participants completing bilateral energy transactions, for
use by the Independent Transmission Provider in completing energy sales and
purchases through its bid-based energy markets, and for providing ancillary
services. The markets should be
operated jointly to ensure that transmission and generation capacity is
allocated where it is most valuable, and to ensure that the prices for the
products and services are internally consistent.
a. Scheduling Transmission Service Day
Ahead
(1) General
Features
3. Each day the
Independent Transmission Provider would accept requests to schedule
transmission service to support bilateral energy transactions or customer-owned
generation for each hour of the following day.
A customer desiring transmission service would be required to submit a
scheduling request in a standardized form specified by the Independent
Transmission Provider. For each
requested transmission service, the scheduling request would indicate the
receipt point and the delivery point of the bilateral energy transaction or
customer-owned generation, the amount of power (MW) to be transmitted and the
time period. To facilitate the ability
of demand to respond to price signals, transmission customers will be given
several ways of indicating their willingness to change their consumption based
on congestion costs and marginal losses:
(1) customers (whether or not they hold Congestion Revenue Rights) would
be allowed to specify in their scheduling requests the maximum transmission
usage charge (reflecting the costs of congestion and marginal losses) at which
the customer desires service;139 (2) customers would be
allowed to specify the maximum congestion charge component of the transmission
usage charge at which they desire transmission service, or above which they are
unwilling to pay any congestion costs; or (3) customers (whether or not they
hold Congestion Revenue Rights) could submit a bid that states a desire for
transmission service to be scheduled regardless of the transmission usage
charge. This option may be useful for a
holder of a Congestion Revenue Right that desires to schedule transmission
service that uses the receipt point-to-delivery point combination covered by
that Congestion Revenue Right.
4. Another way
that transmission customers will be able to respond to price signals is by
submitting multi-hour block bids, requesting transmission service for a block
of consecutive hours and indicating the maximum price for the entire multi-hour
period. For example, a multi-hour block
bid might specify that the customer desires 10 MW of transmission service from
receipt point A to delivery point B in each hour from 1:00 pm to 6:00 pm as
long as the price per MW for the entire 5-hour period does not exceed $10. Such a bid would be accepted if the sum of
the hourly transmission usage prices for each of the 5 hours did not exceed
$10. Otherwise, the entire bid would be
rejected. This option allows a
customer, for example an industrial customer in a state with retail access, to
indicate that it is willing to reduce its transmission usage if the prices for
a multi-hour period are above a specified level. This feature has not been put in practice in any of the bid-based
markets operated by ISOs. We seek
comments on its merit and any implementation difficulties.
5. The
Independent Transmission Provider would consider these transmission scheduling
requests in conjunction with bids submitted in its day-ahead energy and
ancillary service markets. Based on all
of these, the Independent Transmission Provider would accept the set of energy
bids and scheduling requests and develop a day-ahead schedule that maximizes
the economic value for all market participants. The Independent Transmission Provider would also establish
transmission usage prices for each hour of the next day that are the same as
the implicit transmission usage price included in the set of locational energy
prices (i.e., the difference in the price of energy at the receipt point
and at the delivery point, which reflects both congestion and losses).
6. The
Independent Transmission Provider would schedule all requests for transmission
service since these users have agreed to pay any applicable congestion
charges. The Independent Transmission
Provider would also schedule all requested transactions where the transmission
usage charge was below the amount the customer indicated it was willing to
pay.
7. Customers with
Congestion Revenue Rights would receive congestion revenues that help offset
any congestion charges paid as part of the transmission usage charge. The amount of the congestion revenues
received (and the associated protection against congestion charges) would
depend on the specific Congestion Revenue Rights held. A customer holding receipt point-to-delivery
point Congestion Revenue Rights for a certain amount of power between a
delivery and receipt point that matches its day-ahead transmission schedule
would receive congestion revenues that exactly offset its congestion charges,
so that its net bill would reflect no congestion charges (although it would be
charged for losses).
8. The above
process would be used for scheduling transmission service on a daily
basis. Some customers, particularly
those with Congestion Revenue Rights, may desire to schedule the same exact
service over a longer period to save on administrative costs. The Commission seeks comments on whether a
customer should be allowed to provide a schedule for multiple days or have a
standing scheduling request that would remain in effect until changed by the
customer. Any schedule request, once
scheduled by the Independent Transmission Provider would become financially
binding on the customer at the close of each day's day-ahead market.
(2) Transmission Service Across Borders
9. Transmission
service across the border of adjoining Independent Transmission Providers’
service areas – from a point of receipt in one service area to a point of delivery
in another – requires coordination between the affected Independent
Transmission Providers. When
transmission congestion exists between a point of receipt and a point of
delivery in different service areas, managing the congestion becomes more difficult
because more than one Independent Transmission Provider is involved.
10. There
are at least two methods for arranging for transmission service across borders
– physical reservations (i.e., continuing firm point-to-point
reservations of transfer capability), and scheduling of service consistent with
internal transactions under Network Access Service (scheduling of transmission
and financial bidding). We propose to
treat transmission service across borders in the same way as internal
transactions. Thus, like internal
transactions, an importing or exporting customer could either schedule
transmission service and agree to pay the transmission usage charge regardless
of the level or submit a bid that limits its congestion exposure. Under the first method, the transmission
customer would submit to each Independent Transmission Provider a request to be
scheduled for transmission service to and from the border, regardless of the
applicable transmission usage charges that it will be assessed. The customer would be scheduled unless
congestion arose that could not be relieved through redispatch or some other
means. Under the second method,
financial bidding, the customer would submit a price bid to each Independent
Transmission Provider indicating the maximum transmission usage charge that it
is willing to pay for transmission service on each side of the border. The customer would be scheduled if its price
bid on each side of the border was at or above the applicable transmission
usage charge. Under either method, if
the customer's transaction is scheduled, the customer would pay the applicable
transmission usage charges to and from the border. We propose to make both options available to transmission
customers, because each option may provide benefits to customers. We would prefer "one-stop
shopping" with Independent Transmission Provider coordination; we seek
comment on whether this can be done?
11. Recently we accepted a prescheduling option
for service across borders that was proposed by the New York ISO.140 A
prescheduling option would give a customer certainty prior to the day-ahead
market that it could transmit power across a border. Under the New York ISO's prescheduling option a customer may
schedule such a transaction up to eighteen months in advance of the dispatch
day. A customer that requests a
prescheduled transaction agrees to pay the applicable market clearing
transmission usage charge. Once
submitted, the transaction would be financially binding unless the New York ISO
permits the customer to withdraw the prescheduled transaction. We seek comment on whether a similar
prescheduling option should be included in Standard Market Design.
b. Transmission
Losses
12. When
energy is transmitted from a point of receipt to a point of delivery, some of
the energy is lost due to resistance on the wires. These transmission losses are a cost of transmission and commonly
are recovered on an average cost basis from all transmission customers. As noted earlier, we are proposing that
energy prices and the associated transmission usage charges be based on
marginal costs, in order to promote economic efficiency. We seek comment on whether transmission
losses should be recovered on the basis of the marginal cost of losses or if
they should be recovered on the average cost of losses. There are advantages and disadvantages to
each approach. Using marginal losses
would promote a more efficient use of the transmission system. However, as discussed below, charging
marginal losses will collect surplus revenues that must then be returned to
transmission customers. On the other
hand, the advantage of charging average losses is simplicity. If average losses are charged, the losses
collected from customers would equal actual losses. There would be no need to create a mechanism to return surplus
losses.
13. For
customers purchasing transmission service to complete bilateral transactions,
we see value in allowing transmission customers to pay for their assigned
losses either in cash or in kind. To
pay in cash, the customer would pay the market price for its assigned MWhs of
losses, which would be included in the applicable transmission usage
charge. Thus, the MWh of energy
injected at the point of receipt would equal the MWh withdrawn at the point of
delivery. The transmission provider
would procure the energy used for losses from its energy market. To pay in kind, the customer would supply
energy at the point of receipt in the amount of its assigned losses. Thus, the MWhs injected at the point of
receipt would exceed the MWhs at the point of delivery by the amount of the
assigned losses, and the customer would pay in cash only the congestion
component of the transmission usage charge.141
We note, however, that some commenters in our outreach process expressed
concern that allowing customers to provide losses in kind may unduly complicate
the scheduling process, especially for transactions that involve multiple
Independent Transmission Providers. We
seek comment on whether transmission customers should have the choice of paying
for losses in cash or in kind, or alternatively, whether all transmission
customers should be required to pay for losses in cash.
c. Day-Ahead Energy Market
(1) General
Features
14. We
propose that the Independent Transmission Provider be required to run a
voluntary, bid-based, security-constrained day-ahead energy market. "Voluntary" means that market
participants do not have to buy or sell in the day-ahead energy market. The day-ahead market we are proposing
provides customers with additional supply choices. It is not intended to substitute for other longer-term
arrangements that customers may use to purchase supplies such as bilateral
transactions or use of a customer's own generation. Thus, market participants would be able to schedule bilateral
transactions and/or their own generation rather than bid into the day-ahead
energy market. "Bid-based"
means that participants may submit offers to buy or sell quantities of energy
into the market and may specify the prices at which they are willing to
transact. This provides an organized
and transparent system for the Independent Transmission Provider to determine
the marginal cost of relieving transmission congestion. "Security-constrained" means that
the Independent Transmission Provider, in the energy auction process, takes
account of all system constraints, such as contingency limits, needed for
reliable system operations and develops a schedule that does not violate such
constraints. This is necessary to
ensure that the day-ahead schedule is physically feasible. Otherwise, the Independent Transmission
Provider might be required to make additional payments in real time to relieve
congestion, which could provide an incentive for market participants to create
congestion in the day-ahead market to receive these payments in the real-time
market.142 The market should allow
full participation by both the supply side and the demand side of the
market.
(2) Bidding and Scheduling Rules
15. Each
day, the Independent Transmission Provider would accept bids to sell and buy
energy for each hour of the following day.
Participants desiring to sell or buy energy would submit a bid in a
standardized form.
16. Each
seller's bid would indicate the amount of power (MW) offered to be sold, the
receipt point, and the time period. In
addition, each seller would be allowed to submit multi-part bids that
separately specify bid prices for start-up, no-load, and energy, as well as
technical characteristics such as ramp rates, minimum run times and minimum
down times. Allowing suppliers' bids to
include these items yields more detailed information that can improve the
ability of the grid operator to dispatch suppliers with the lowest total cost. For example, if the supplier were required
to submit a one-part bid it would need to include start-up costs in its energy
bid, resulting in a higher energy price bid.
However, a supplier submitting a bid that separately specified the
energy bid and the start-up costs would not have to make these estimates and
the grid operator would use the bids to dispatch the supplier with the lowest
total cost. Suppliers would also be
allowed to submit bids that are self-schedules, that is, that would indicate an
amount to be supplied at a location regardless of the applicable energy price. The supplier would receive the applicable
market clearing price for its energy.
This option may be useful for suppliers with very high start-up costs
such as nuclear facilities.
Intermittent resources would be able to participate in the day-ahead market
on the same basis as other resources.
17. Similarly,
each buyer's bid would indicate the desired amount of power (MW) to be bought,
the delivery point, and the time period.
In addition, each buyer would be allowed to specify bid prices that
indicate the quantities it is willing to purchase at alternative prices. Buyers would also be allowed to submit
multi-part bids that indicate the time and price constraints under which they
are willing to purchase energy. These
options would facilitate demand response programs because they allow the buyer
to indicate the price at which it will voluntarily reduce its consumption. Buyers would also be allowed to schedule an
amount to be purchased regardless of the applicable energy price.143
Bids would not need to be tied to a physical generator or load
resource. However, for reliability
purposes, bids would need to indicate whether they were purely financial bids
or whether they were tied to a physical resource. This would permit market participants to bring day-ahead and
real-time prices closer together, increasing the stability of both
markets. This option should reduce
price differences between these two markets.
18. Buyers
and sellers would be able to submit different price bids for different hours of
the day, and bids could vary from day to day.
However, if market participants can exercise market power, limits may be
imposed on bidding to mitigate market power, as discussed below in the section
addressing market power monitoring and mitigation.
19. We propose a scheduling option to address the
special conditions facing energy-limited resources such as hydroelectric and
environmentally constrained thermal resources.
These resources are limited in the amount of energy or the number of
hours that they can produce energy over a period of time. As a result, production in one hour may
reduce the amount of energy that the resource can produce (and the associated
revenue) in other hours. Energy-limited
suppliers could submit bids in the day-ahead market that specify the amount of
energy, or the number of hours, available for production over the next
day. The supplier could then request
the Independent Transmission Provider to schedule its energy in those hours of
the next day when the energy price is highest.
Such a scheduling feature would promote efficient scheduling because it
would allow the energy-limited resource to be scheduled where its energy would
have the greatest value, with maximum profit to the resource owner.144
We recognize that the resource mix varies significantly from region to
region and that some regions, such as the Northwest, have a greater amount of
energy limited resources. We seek comment on whether other scheduling options
or regional variations should be included for energy-limited resources in the
tariff.
20. We
recognize that intermittent resources such as wind power may also benefit from
scheduling rules that recognize their inability to precisely control
output. We recently approved a special
mechanism for intermittent resources selling into the energy market run by the
California ISO.145 Under that mechanism, the
intermittent resource and the California ISO work together to develop a
schedule and procedures for accurately forecasting the output of the
resources. However, California ISO
currently runs only a real-time market for energy and not both a day-ahead
market and real-time market as proposed here.
Also, the amount of power produced by intermittent resources within
California is much larger than in many parts of the country. We propose to include the California ISO's
scheduling option for intermittent resources as part of Standard Market
Design. However, we seek comment on
whether there is a better way to schedule intermittent resources.
21. Finally,
in drafting the bidding and scheduling rules we have included several ways for
demand to respond to prices. We
recognize that several ISOs currently have demand response programs that
operate differently. Under these demand
response programs, the ISO pays end-users to reduce their demand if market
clearing prices reach a certain level.
We believe the direct approach of letting demand bid in the market will
be less costly than a program where an end-user receives payments greater than
the market clearing price to reduce its demand. We have not proposed to include these types of programs in the pro
forma tariff although they could be included if the Independent
Transmission Provider, in consultation with the state advisory committee and
stakeholders, determined that they were necessary. Since the participation of demand in the market is critical for
an effective wholesale market, we seek comment on whether the measures proposed
are sufficient or if other measures should be included.
(3) Price Determination and Settlement
22. Based
on the accepted bids included in the day-ahead schedule, the Independent
Transmission Provider would establish day-ahead locational energy prices for
each hour. The hourly energy price at
each location would reflect the marginal cost (as reflected in bids) of
producing and delivering energy to that location in that hour. Energy prices would be consistent with the
transmission usage charges, so the difference in energy prices between two
locations in an hour would reflect the cost of transmitting energy from one
location to the other.
23. The
Independent Transmission Provider would establish a single market-clearing
energy price for each hour for each node on its transmission system. We believe it is important that energy
prices be calculated for each node to avoid socialization of congestion costs
and to reduce the possibility of manipulating the congestion management system.146
The Independent Transmission Provider could also establish nodal prices
for time intervals shorter than an hour.
Nodal pricing would be used for both buyers and sellers in the day-ahead
market.
24. Upon
request of market participants, the Independent Transmission Provider would
establish trading hubs. A trading hub
is a virtual location where financial transactions may be arranged, whose hub
price is the weighted average of energy prices at a specified set of nodes on
the transmission system. A trading hub
facilitates financial trading and aggregation of supplies from multiple
sources. Creation of trading hubs
should not lead to socialization of congestion costs, because the price for
service at the trading hub is the weighted average of prices at the various
nodes that are included in the trading hub.
Energy may not be injected or withdrawn from the grid at a trading hub,
since a hub does not exist at a physical location. But a hub may be named as an intermediate point between physical
points of injection and withdrawal where financial energy trades may occur.147
Also, at the request of market participants, the Independent Transmission
Provider would establish zones that are the weighted average of energy prices
at selected delivery nodes on the transmission system. This option would permit a load-serving
entity to aggregate prices for deliveries to its various delivery nodes.
25. Each
buyer and seller would transact at the applicable clearing price for the hour
and time period. A seller that submits
separate bids for start-up and no-load costs and is dispatched by the
Independent Transmission Provider for any period during the day, will be
assured that it will recover the start-up and no-load costs that it bid. If a seller’s total bid costs (including
start-up and no-load costs, as well as energy running costs) over the entire
day are not fully covered by its revenues from selling at the hourly clearing
prices, it would receive an additional payment (i.e., an
"uplift" payment) for the net revenue shortfall for the day. Hourly energy prices would be based only on
energy bids; start-up cost bids and no-load bids would not be used in
calculating hourly energy prices. Thus,
a generator may have legitimate start-up costs that are not fully covered by
selling at the hourly energy price over the day; paying uplift may be necessary
to ensure that generators selected in the auction will receive revenues that
fully cover their bid-costs.148 Since the additional
payments are a cost of providing supplies of energy and ancillary services in
the Independent Transmission Provider's day-ahead market, we propose to recover
the additional payments from entities that purchase energy and/or ancillary
services in the Independent Transmission's Provider's day-ahead market. Any entity that does not buy any energy from
the Independent Transmission Provider's day-ahead market on a given day, and that
self-supplies all of its ancillary service obligations on that day, would not
be assigned a share of the additional payment for that day.
26. The
results of the day-ahead market would be financially binding on buyers and
sellers. That is, sellers would be paid
the applicable locational day-ahead price for energy scheduled to be sold in
the day-ahead market, and buyers would pay the applicable locational day-ahead
price for energy scheduled to be bought in the day-ahead market. In addition, to the extent sellers and
buyers fail to actually produce or take energy according to their respective
schedules in real time, such imbalances would be settled at the applicable
real-time energy price. Thus, a seller
would pay the real-time LMP nodal price for any scheduled energy that it fails
to deliver in real time to its bid delivery point. Similarly, a buyer would be paid the applicable LMP nodal
real-time price for any scheduled energy that it does not take at its bid receipt
point in real time.
27. The
Independent Transmission Provider would post prices and other market
information and settle the markets promptly to provide market participants with
reliable information regarding their market transactions.
28. In
certain instances, a generator may alleviate a voltage or stability constraint
by producing real power and/or reactive power at its location. By alleviating the constraint, the transfer
capability of the grid may be increased, thereby allowing a greater amount of
lower-cost energy to be transmitted to an area with higher energy prices. For example, the transmission capability to
import power into a load pocket may initially be limited to 1000 MW due to a
voltage or stability constraint, even though the thermal limit is 1500 MW. However, production of an additional 100 MW
of real power and/or an additional amount of reactive power within the load
pocket could increase import capability into the load pocket by 50 MW, to 1050
MW. We seek comment on whether
generators who provide such real or reactive power should receive additional
compensation (in addition to the locational market price for energy and the
applicable compensation for reactive power) for the additional transfer
capability that they create, to provide incentives to produce energy that
increases transfer capability. For
example, should such generators be given the Congestion Revenue Rights with the
additional transfer capability that they create? In certain circumstances, a generator must reduce its production
of real power in order to increase its production of reactive power. In these circumstances, should the generator
be compensated for the opportunity cost of its reduced profits from selling
real power? Should the generator be
paid the higher of its opportunity costs or the market congestion value of the
additional transfer capability created?
How should locational market power concerns be addressed in these
circumstances?
d. Day-Ahead Ancillary Service Markets
(1) General
Features
29. Order
No. 888 identifies six ancillary services, two of which may only be provided by
the Independent Transmission Provider and four of which must be offered by, but
need not be obtained from the Independent Transmission Provider. The four ancillary services that must be
offered by, but need not be obtained from the Independent Transmission
Provider, include:149
(1) Regulation and frequency response
(2) Energy imbalance
(3) Operating reserve -
spinning
(4) Operating reserve -
supplemental
Pursuant to the requirements of Order No.
888, transmission customers are assigned the responsibility for these ancillary
services. Customers may meet their
responsibility through self-supply, by procuring these ancillary services from
a third party, or by acquiring them from the Independent Transmission Provider.
30. As discussed earlier, imbalance energy would
be provided through the day-ahead and real-time energy markets. For the remaining three ancillary services
(regulation and both operating reserves), we propose to require that the
Independent Transmission Providers operate bid-based markets open to all
potential suppliers so that Independent Transmission Providers can procure
these ancillary services from the lowest cost suppliers. Different regional reliability authorities may
establish different requirements for operating reserve - supplemental. For example, the four jurisdictional
operating ISOs procure resources for the ancillary service operating reserve -
supplemental (which are usually generation resources that are not synchronized
with the grid or demand-side resources that can curtail use), with varying
response times. Each ISO procures a
portion of their necessary operating reserve - supplemental requirement with
reserves that can respond within 10 minutes of a dispatch request, as well as
slower-responding reserves at 30 minutes (New York ISO and ISO-New England) and
60 minutes (California). Since
different regional reliability authorities have established different response
times for operating reserve - supplemental, we do not propose a standard set of
markets for operating reserve - supplemental.
However, we propose to require that each Independent Transmission
Provider operate separate markets for each type of operating reserve -
supplemental that it procures.
31. Location-specific
reserve targets may be required in some areas due to persistent and significant
congestion. The Independent
Transmission Provider would identify and establish these targets consistent
with any reliability rules.
(2) Bidding and Scheduling Rules
32. Each
day, the Independent Transmission Provider would determine the total amount of
each of the ancillary services that will be required for each hour of the
following day. Customers that wish to
meet their ancillary service requirement through self-supply or procurement
through a third party would be required to provide the Independent Transmission
Provider with the necessary information about the generation capacity or
demand-side resource that would be providing the ancillary services (as is
currently required under the existing pro forma tariff).
33. To
procure the remaining amount of ancillary services, the Independent
Transmission Provider would accept bids for regulation and the types of
operating reserves for each hour of the following day. A participant desiring to sell regulation or
operating reserves would submit a bid in a standardized form specified by the
Independent Transmission Provider. Bids
could be offered to provide ancillary services from generation capacity or any
demand-side resource that meets the technical requirements of the ancillary
service. Participants could offer the
same capacity in more than one ancillary service market, as well as in the
energy market.
34. Each
bid would indicate the type of ancillary service, the amount of generating
capacity (MW) offered for sale, the receipt point of the resource and the time
period. The bid would also include an
availability bid indicating the minimum price per MW (which could be either a
positive amount or zero) required to provide the ancillary service. The availability bid would allow the bidder
to ensure that it would not be selected to provide the ancillary service unless
the ancillary service price is high enough to cover out-of-pocket costs, such
as the costs of keeping a crew at its facility for the following day. The bid would also include the various
components that would be submitted to provide energy into the energy
market. These components include an
energy bid, indicating the minimum price per MWh required to produce
energy. Other bid components would
include price-bids for start-up and no-load, as well as technical constraints,
such as minimum load, ramp rates, minimum run time and minimum down time. By providing one ancillary service, a bidder
may forgo profits from sales in other markets, and these forgone profits are an
opportunity cost of providing ancillary services. As explained in the following section, the Independent
Transmission Provider will consider the opportunity cost associated with
forgone sales in other markets operated by the Independent Transmission
Provider. Opportunity costs from
forgone sales in markets not operated by the Independent Transmission Provider
could be included in the bidder's availability bid.
35. The
Independent Transmission Provider would consider all bids to sell ancillary
services, in conjunction with bids submitted in its day-ahead markets for
energy and transmission service. As
noted earlier, based on all submitted bids, the Independent Transmission
Provider would maximize the economic value (as reflected in the bids) of the
accepted bids, i.e., accept the bids with the overall lowest cost. Thus, for generation capacity and
demand-side resource that bid into more than one market, the Independent
Transmission Provider would schedule the generation capacity or demand-side
resource into the market where it is most efficient (unless it is not efficient
to schedule the generation capacity or demand-side resource in any market).150
This should yield the overall lowest cost for procuring energy,
regulation and operating reserves.
(3) Price Determination and Settlement
36. Based
on the accepted bids included in the day-ahead schedule, the Independent
Transmission Provider would establish day-ahead prices for each of the
ancillary services procured in the bid-based markets for each hour. In regions with separate locational
ancillary service requirements, the Independent Transmission Provider would
establish separate hourly locational ancillary services prices.
37. To
promote an efficient market, the price for regulation and operating reserves
services would equal the marginal cost of each service, which would equal the
highest accepted total bid cost expressed in dollars per MW. The total bid cost of each generator is the
sum of: (1) the generator's
availability bid per MW and (2) the opportunity cost of forgoing sales in other
markets operated by the Independent Transmission Provider, expressed on a
per-MW basis.151
38. A
generator or demand-side resource could be eligible to bid into more than one
market operated by the Independent Transmission Provider. The opportunity costs paid to the supplier
would be the forgone profit from the most profitable other market. For example, a generator that is capable of
providing ancillary services could also sell into the transmission provider's
day-ahead energy market, although it would incur additional variable energy
costs to do so. Thus, the forgone
profit from selling into the energy market (as reflected in the generator's
bid) would be the difference between the energy price and the generator's
energy bid. The opportunity cost of
selling ancillary services would include this forgone energy profit.
39. The
hourly price for one of these ancillary services in a given location would thus
equal the sum of the opportunity cost and the availability bid in dollars per
MW of the most expensive unit accepted to provide that type of ancillary
service in that hour to that location.
As noted above, a generator providing any ancillary service is also
technically capable of providing a slower response ancillary service. For example, a generator providing operating
reserve - spinning could also provide operating reserve - supplemental. Thus the opportunity cost of providing
operating reserves - spinning would be at least as high as the price of
operating reserve - supplemental. As a
result, the marginal cost (and thus, the price) of operating reserve - spinning
would not be less than the price of operating reserve - supplemental in the
same hour.
40. Although
suppliers bid to provide these ancillary services in the day-ahead market,
customers pay for them based on real-time load. Transmission customers would be assessed a pro rata
share of the total ancillary service requirements for each of these three
ancillary services in each hour, based on their real-time, load-ratio
share. Ancillary service requirements
generally depend more on real-time transactions than on day-ahead
schedules. Assessing ancillary service
requirements based on day-ahead schedules would provide an incentive for customers
to understate their day-ahead schedules.
41. In
Order No. 888, exports are not charged for these ancillary services. We ask for comments on whether they should
be charged here.
42. Customers
that want to self-provide or procure their own ancillary services would be
required to notify the Independent Transmission Provider in the day-ahead
scheduling process and identify the resources that would be used to provide
these services. Customers would be
given credit for the amount of ancillary services that they self-provide or
procure from third parties. Customers
that self-provide or procure from third parties more capacity than their
requirements would be paid the applicable hourly ancillary service price for
the excess if needed by the market.152
2. Scheduling After the Close of the
Day-Ahead Market
a. Replacement Reserves
43. The
Independent Transmission Provider will use the day-ahead market to develop
prices and a schedule for suppliers.
The prices and schedules will be based on the bids submitted by buyers
and sellers. However, the day-ahead
schedule may be less than the forecasted load in real time and, if so, the
Independent Transmission Provider would commit additional units to ensure that
load can be met reliably in real time.
44. After the Independent Transmission Provider
has established a day-ahead schedule and associated prices for energy,
transmission service and ancillary services, it would make its own forecast of
load within its market area for each hour of the following day. To the extent that its forecasted load
exceeds the amount of energy scheduled to be delivered to load in the day-ahead
schedule, the Independent Transmission Provider may need to procure additional
reserves (called "replacement" reserves) from generators to make up the
difference, but only to the extent necessary to ensure that sufficient
generation will be available to meet load.
45. To
procure replacement reserves, the Independent Transmission Provider would
accept bids from generators submitted for the day-ahead market. The Independent Transmission Provider would
select generators to provide replacement reserves so as to minimize the costs
of availability, start-up costs and no-load costs regardless of energy costs. This approach to procuring replacement
reserves would provide an incentive for load to accurately bid its load in the
day-ahead market since energy prices may be higher in the real-time
market.
46. As
discussed further in the next section, generators selected to provide
replacement reserves would be included in the real-time energy bid stack along
with other generators that submit bids into the real-time market to provide
energy. Generators selected to provide
replacement reserves would be paid the applicable real-time energy price for
energy that they produce. If a
generator's revenues received from selling real-time energy are less than its
bids for availability, start-up, no-load and energy, the Independent
Transmission Provider would pay the generator an additional payment (i.e.,
an "uplift" payment) for the shortfall. The revenue shortfall would be recovered pro rata
from all loads that buy energy in real time that have not been scheduled in the
day-ahead market. Thus, the costs would
be allocated to the customers that benefitted from the replacement reserves –
customers that took power in real time.
This provides an incentive for load to accurately predict its
requirements in the day-ahead market.
47. We
propose to add a new Section G.2 to the pro forma tariff that
would implement the foregoing procedures for scheduling and paying for reserves
after the close of the day-ahead market.
b. Changes
to Transmission Schedules
48. A
market participant that has not scheduled transmission service in the day-ahead
market but desires transmission service in real time must inform the
Independent Transmission Provider within specific time deadlines before real
time. Market participants may change
their day-ahead transmission service schedule by informing the Independent
Transmission Provider consistent with the time deadlines.
49. Participants
that have informed the Independent Transmission Provider of their desired
changes within the Independent Transmission Provider's lead times, and adhere
to the requested changes in real time, would settle the changes in transmission
service at the applicable real-time transmission usage prices, described more
fully below. Participants with new or
increased transmission service would be charged the applicable real-time
transmission usage price between the applicable receipt and delivery points for
the new or increased transmission service in the applicable hour. Conversely, participants that reduce
transmission service in real time (compared to the day-ahead schedule) would be
paid the applicable hourly real-time transmission usage price for the
applicable receipt and delivery points, to compensate them for the additional
transmission capacity they have made available in real time.
3. Design of
the Real-Time Markets
50. Under
Standard Market Design, the Independent Transmission Provider would be required
to operate bid-based, security-constrained real-time markets for transmission
service, energy, and certain ancillary services (i.e., regulation,
operating reserve - spinning and operating reserve - supplemental).
a. Real-time
Energy Markets
(1) General
Features
51. Under
the Standard Market Design, the Independent Transmission Provider would accept
bids to buy and sell energy in each hour in the real-time energy market. The bids would be in the standardized form
specified by the Independent Transmission Provider. Real time energy markets would be used to provide the imbalance
energy service of Order No. 888 pro forma tariff and self
provision would be allowed. However,
loads could voluntarily enter into bilateral contracts with suppliers in
advance to lock in a fixed price for energy.
(2) Bidding
and Scheduling Rules
52. In
general, bids would indicate an offer to depart in real time from the bidder's
day-ahead schedule to purchase or sell energy (including a day-ahead schedule to
purchase or sell 0 MWhs of energy).
Real-time bids would be accepted from any market participant, including generators,
load-serving entities, eligible retail buyers, marketers and other agents. Bids would indicate the increase or decrease
(in MWhs) from the day-ahead schedule in the amount of energy to be sold or
purchased in real time, and the location and the hour of the changed purchase
or sale. Each participant bidding into
the real-time energy market would be allowed to include multi-part price bids
similar to those allowed in the day-ahead energy market (this is a departure
from the Working Paper).
53. The
transactions in real time vary from those reflected in the day-ahead schedule
due to a variety of factors, including changes in weather conditions and
unexpected equipment outages. The
Independent Transmission Provider may be informed in advance of some of the
scheduling departures under the procedures described above; other departures
may occur without warning.
54. As
occurs today, an Independent Transmission Provider will have to adjust energy
production and/or load at various locations in order to balance generation with
load and manage congestion. Under
Standard Market Design, the Independent Transmission Provider would make these
adjustments by calling upon participants that have submitted bids into the
real-time energy market, as well as participants that have been selected to
provide spinning, supplemental, and replacement reserves. The Independent Transmission Provider would
issue dispatch instructions to bidders so as to balance generation and load,
and efficiently manage congestion of demand and supply.
(3) Price
Determination and Settlement
55. The
Independent Transmission Provider would determine energy prices in the
real-time energy market for each node for each 5-minute period or other
subhourly period where a 5-minute determination is not technically
achievable. Each price would reflect
the marginal cost (as reflected in the real-time supply and demand bids) of
producing energy and delivering it to the node in that period. The Independent Transmission Provider would
post prices and other market information and settle the markets promptly to
give market participants reliable information regarding their market
transactions.
56. To
promote efficient participant decisions regarding real-time transactions, we
propose that all departures in real time from the day-ahead schedule be settled
through the real-time market at the applicable price (as is done today in many
markets). Nodal pricing would be used
for both buyers and sellers in the real-time market.
57. There
are several aspects of the design of the real-time energy market where we seek
additional comments.
Ex
Post versus Ex Ante Prices
58. This
Section discusses how to determine real-time energy prices. The options are to set the prices using near
real-time estimates (ex ante), or base the price on the price of
the actual marginal resource clearing the market in real time (ex post).
Immediately in advance of each upcoming 5-minute period, the Independent
Transmission Provider would announce the real-time energy prices that it
estimates will clear the market and match generation with load during that
upcoming period (based on the real-time bids submitted by market participants). The Independent Transmission Provider could
settle all departures in real-time from the day-ahead schedule using these
prices announced in advance. Such an ex
ante pricing policy would provide price certainty and thereby encourage
buyers and sellers that have not submitted bids to adjust their transactions in
response to the announced price.
59. Alternatively, an ex post
pricing policy could be used as an incentive for suppliers to follow dispatch
instructions. Some bidders may not
respond to the announced prices in the way suggested in their bids. For example, a supplier stating in its bid
that it would increase its output by 50 MWh for each price increase of $5/MWh
may in fact increase its output by less than 50 MWh in response to such a price
increase. By settling at the ex ante
price, the generator would be paid the higher price despite the fact that it
did not increase its output as it had promised in its bid. An ex post pricing rule might
help to encourage bidders to respond in real time in a way consistent with
their bids. Specifically, the price
used to settle real-time deviations from day-ahead schedules could be the
price-bid associated with the energy observed ex post to be
produced by the marginal supplier in the 5-minute period (but not higher than
the advisory price announced ex ante). Such an ex post price rule would encourage
suppliers to supply the full amount of energy promised in their bids.
60. We
propose to adopt the ex post rule because it creates incentives
for bidders to act consistent with their bids.
We seek comment on the choice between ex post and ex
ante pricing.
Other
Charges for Uninstructed Deviations from Schedules
61. We
seek comment on whether market participants should face additional charges for
“uninstructed” deviations in real time from their schedules, i.e., for
producing or taking a different amount of energy in real time than was
scheduled without permission or direction from the Independent Transmission
Provider. Uninstructed deviations from
schedules may increase the amount of regulation service or other ancillary
services that the Independent Transmission Provider must procure, in order to
reliably balance load and generation.
If so, it would be appropriate to recover the costs of these services
through a charge. We seek comment on
whether the increased costs of regulation service or ancillary services should
be allocated to the entities (buyers and sellers) that had uninstructed
deviations from their schedules since the costs were incurred to serve these
entities. Uninstructed deviations may
also require the use of scarce ramping capability within the Independent
Transmission Provider’s market area. If
ramping capability were used, it may be appropriate to charge for that use. We seek comment on whether and how to establish
market prices for ramping capability.
Finally, in extreme cases large uninstructed deviations can threaten
reliability of service. To discourage
this type of conduct a penalty provision may be appropriate.153
We seek comment on whether the SMD Tariff should include penalty
provisions for uninstructed deviations that threaten system reliability and how
such penalty provisions should be structured.
What Bids Should be Eligible
to Set the Energy Price
62. Strictly
speaking, the marginal cost of meeting a small increment of load would be based
on the bids of suppliers whose output can be increased, or buyers whose load
can be decreased, from their scheduled level in the hour by as little as 1
MW. Thus, for example, the marginal
cost of supplying load in an hour would not be based on the bid of any
generator that is operating in the hour solely because of a minimum run
constraint, because changes in load would not change the output of the
generator.154
63. However,
we are concerned that by excluding generators whose output is adjustable in
increments greater than 1 MW, on an hourly basis, from setting the energy price
may not promote efficient results.155
These potential inefficient results are more likely to occur in the
real-time market than in the day-ahead market.156
Therefore, we propose to allow generators whose output is adjustable on
an hourly basis, but only in increments greater that 1 MW, to be eligible to
set the energy price in the Real-Time Market if two conditions are met. First, the generator’s output must be needed
to meet load in the hour. That is, in
the absence of the generator’s output, either load could not be fully met or a
more expensive generator would be needed to fully meet load. Second, the reason that the generator is
operating must not be a minimum run time constraint. We also propose that any cheaper generators that are directed to
reduce their output would be paid their opportunity costs (i.e., the
difference between the applicable energy price and their energy bids) for the
amount of the output reduction. With
this payment, the generator is compensated for the legitimate opportunity cost
of following the Independent Transmission Provider's instructions.157
64. We
seek comment on whether such lumpy generators should also be eligible to set
the energy price in the day-ahead market.
Although allowing these lumpy generators to set the energy price may
have more direct benefit in the real-time market, we are concerned about
potential negative ramifications from establishing different pricing rules for
the day-ahead and real-time markets.
b. Real-Time
Ancillary Services Markets
65. As
discussed earlier, Order No. 888 requires transmission providers to offer to
provide to transmission customers energy imbalance service, regulation and
frequency response, operating reserve - spinning and operating reserve -
supplemental. Under Standard Market
Design, energy imbalance service would be provided through the transmission
provider's real-time energy market. The
Independent Transmission Provider would procure its expected requirements for
the remaining three ancillary services through day-ahead ancillary service
markets discussed above.
66. We
propose that the Independent Transmission Provider operate a real-time
ancillary services market to accommodate adjustments in the supply of ancillary
services from the day-ahead schedule.
In real time, there may be entities that can provide ancillary services
more efficiently than those that were scheduled in the day-ahead market. The real-time market would permit such
efficient substitutions. Higher-cost
suppliers scheduled in the day-ahead market would buy back their offer to
provide ancillary services at the applicable real-time price, and other,
lower-cost entities would be paid the real-time price to take over the supply
of ancillary services. In addition, the
Independent Transmission Provider may need an amount of ancillary services that
differs from the amounts procured in the day-ahead market, for several
reasons. For example, the requirements
expected in the day-ahead market may differ from actual, real-time
requirements, or participants scheduled to provide ancillary services may
experience outages in real time. Under
Standard Market Design, the Independent Transmission Provider would procure any
additional ancillary services needed in real time through the real-time
ancillary service markets that it operates.
67. In
the real-time market, the Independent Transmission Provider would accept bids
for each ancillary service. As in the
day-ahead market, a participant could offer the same capacity in more than one
ancillary service market. The real-time
bids would contain the same types of information as those submitted into the
day-ahead ancillary service markets, with one exception – we propose to exclude
availability bids for spinning reserves and supplemental reserves in real
time. The types of costs reflected in
the availability bid to ensure that the supplier will be available to provide
these reserves are incurred in the day-ahead time frame, not in real time.158
There do not appear to be any incremental costs associated with
providing these ancillary services in real time, other than the opportunity
costs of forgoing sales in another market operated by the Independent Transmission
Provider, and these opportunity costs would be reflected in the way that
ancillary service prices are determined.159
68. The
Independent Transmission Provider would consider all bids to sell ancillary
services in real time and select those bids that minimize the overall cost of
procuring additional ancillary services required in real time.
69. Based
on the bids accepted in the real-time market, the Independent Transmission
Provider would establish real-time ancillary service prices for each hour that
reflect the marginal cost of each service.
All participants supplying a given type of ancillary service in a given
hour in real time (and to a given location, if there are locational ancillary
service requirements) would be paid the applicable market clearing price.
70. Transmission
customers that have not self-supplied or procured through third parties their
full assigned ancillary service requirement would be assessed a pro rata
share of the costs incurred by the Independent Transmission Provider for
procuring ancillary services in real time.
4. Market
Rules for Shortages or Emergencies
71. We believe the market rules discussed above
in combination with the market mitigation measures and the resource adequacy
requirement will result in an efficient system for matching supply and demand
under most operating conditions.
However, we recognize that when emergency situations do occur, changes
may be needed to the market rules to comply with reliability requirements. In the event of a capacity shortage or
emergency, local reliability rules and procedures (which typically combine
NERC, regional reliability council and system operator guidelines) prescribe a
series of actions that the system operator takes to maintain reliability. For example, procurement of reserves is
reduced, typically in order of reserve quality (that is, supplemental reserve
quantities are reduced before spinning reserve quantities). The system may be re-dispatched to adjust
the location and responsiveness of remaining reserves. System operators have also traditionally
called on emergency supplies from neighboring systems (in the past, these
emergency purchases have taken place at pre-defined prices; increasingly, they
are being made at market prices).
Finally, steps are taken for voluntary and involuntary load-shedding. States typically approve in advance the
retail curtailment plans of utilities.
72. In
the markets proposed in the SMD Tariff, we envision that with more extensive
demand-side participation, the potential for these types of capacity shortage
or emergency situations will substantially diminish. However, system emergencies may occur. The existing pro forma tariff gives transmission
providers the authority to curtail transmission service and take any other
preventive action necessary to preserve system reliability. The SMD Tariff would continue to grant the
Independent Transmission Provider this same authority. However, the actions taken to ensure system
reliability can affect prices in the energy and ancillary service markets. Market participants should be aware of how
these actions will affect pricing in the markets operated by the Independent
Transmission Provider. To that end, the
SMD Tariff requires Independent Transmission Providers to file proposals with
the Commission regarding the implications for market pricing of each
reliability procedure. These proposals
would need to be consistent with the resource adequacy mechanisms discussed
below, but could vary to reflect regional differences in reliability
requirements. We seek comments on what,
if any, more specific requirements should be included in the Final Rule.
138Part I of the SMD Tariff includes a definition of the terms related to market services. In addition, as we use the term "supplier" or "seller" in this Section, the definition we are using includes both generators and demand-side resources that satisfy the Independent Transmission Provider's applicable requirements.
139For example, when transmission usage prices become sufficiently high, customers holding receipt point-to-delivery point Congestion Revenue Rights may prefer not to schedule transmission service between their designated receipt and delivery points. Instead, the customers may prefer to receive the applicable congestion revenues. Customers could communicate these preferences through price-bids.
140New York Independent System Operator, Inc., 99 FERC ¶ 61,292 (2002).
141The amount of energy needed for losses would not be known until the close of the market. For transactions in the day-ahead market, the Transmission Provider would inform each customer that wishes to supply losses in kind (after the close of the day-ahead market) of the amount of its assigned losses (in MWh), and that amount would be included in the customer's day-ahead schedule. For transactions in the real-time market, the Transmission Provider could provide an estimate in advance of the amount of each customer's assigned losses. However, since actual marginal losses would not be known until after the fact, the customer would be charged or credited at the applicable LMP for any under- or over-provision of losses.
142See the discussion of this issue in Appendix E.
143Since energy prices have the potential to rise to very high levels, it may be necessary to require buyers that request energy without submitting a price bid to demonstrate to the Independent Transmission Provider in advance that they are financially capable of paying very high prices for such quantities. Alternatively, the Independent Transmission Provider could limit the amounts based on a buyer's creditworthiness.
144While this scheduling feature is intended mainly for energy-limited resources, it would be available to all generators and would not be restricted to energy-limited resources, unless such restrictions are necessary to mitigate market power.
145See California Independent Operator Corp., 98 FERC ¶ 61,327, order accepting compliance filing, 99 FERC ¶ 61,309 (2002).
146 See discussion in Appendix E of manipulation strategies involving congestion management.
147 A good example of a trading hub is PJM's Western hub, where there are active spot energy and transmission rights markets, as well as bilateral markets.
148 For example, suppose that the Independent Transmission Provider needs to supply an additional 100 MW load in each of 20 hours over the next day. Two generators, A and B, are available. Generator A has energy costs of $35/MWh, but must incur $15,000 in start-up costs before beginning production. Generator B has energy costs of $40/MWh, and has no start-up costs. Generator A’s total cost of meeting the load would be $85,000 (i.e., total energy costs of $70,000 [$35/MWh x 100 MWh x 20 hrs] PLUS start-up costs of $15,000). Generator B’s total cost would be $80,000, comprised exclusively of energy costs (i.e., $40/MWh x 100 MWh x 20 hrs). Generator B should be chosen because its total costs ($80,000) would be less than Generator A’s total costs ($85,000). Suppose that the hourly clearing price in each hour is $42/MWh. By selling 100 MWh in each of 20 hours, Generator B would receive total revenues of $64,000 (i.e., $32/MWh x 100 MWh x 20 hrs), which is $6,000 less than its total bid-in costs of $70,000. Generator A would thus need to receive a $6,000 uplift payment in addition to its energy revenues. Paying $6,000 in uplift is still cheaper for customers than the alternative of dispatching Generator B.
149These four ancillary services are in addition to two other ancillary services, (1) Scheduling, System Control and Dispatch Services and (2) Reactive Supply and Voltage Control. We seek comment on treating Scheduling, System Control and Dispatch Services as a basic cost of providing transmission service instead of as an ancillary service.
150Because of the way that prices would be established in each market, the market into which each bidder of generation capacity or demand-side resource is scheduled would also be the market that is the most profitable for the bidder. That is because, as discussed in the following section, the prices in each market would reflect marginal opportunity costs of the bidders in that market. Thus, the price in each market would be high enough to allow each accepted bidder in that market to receive at least as much profit as it could have received in any other market operated by the Independent Transmission Provider that it is technically capable of participating in.